Read the notice and its 1 attached document and pull out the scope, the deadlines and what you have to submit.
Provide and install piping and power for owner provided and installed modular boiler/chiller plant and cooling tower. Connect piping from plant to existing piping serving three campus buildings.
Delivery Method: Design-Bid-Build
Construction Cost Range: $1,250,000 to $1,400,000 Prime Contractor License (Special Standard of Responsibility): N/A
Documents: Email request to meca@mecainc.com. PDF documents will be provided.
We post new hvac opportunities in South Carolina as agencies publish them. Get them in one email — free, and unsubscribe whenever.
Most South Carolina work asks for the two below, and the solicitation documents are where it’s stated. Here’s what each costs through Light RFP if you need one.
Source: Northeastern Technical College (solicitation H59-6217-CB), retrieved via a public procurement portal. View the official posting, and always confirm requirements and deadlines with the issuing agency.