- Scope
- This project is used to repair, replace or remove hazardous roadside elements (guiderail, bridge rail, trees, etc.) as necessary along highways at various locations in Region 2.
- Region
- MOHAWK VALLEY
- Address
- Mohawk Valley Region — Oneida, Madison, Hamilton, Herkimer, Fulton, Montgomery County — NY
- Due Date
- Apr 18, 2025
- Funding
- Local
- No
- State
- Yes
- Federal
- Yes
- Mpo Text
- Statewide Transportation Improvement Program (STIP)
The Statewide Transportation Improvement Program (STIP) is a list of every project
in New York State for which Federal funding is proposed to be used and that is
scheduled to begin during the designated three Federal fiscal year time frame.
To review the STIP Project List by Region please see the
STIP Project Report .
- Award Raw
- 04/18/2025
- Counties
- Oneida, Madison, Hamilton, Herkimer, Fulton, Montgomery
- Overview
- Project Overview
Project Status
- The current status of the project is Under Construction.
- The Bid Opening was on 02/27/2025.
Project Schedule
Award of Contract Original Contract Completion Date*
Estimated Substantial Completion Date*
Construction Schedule Variance from Contract Award** Award of Contract Original Contract Completion Date*
Estimated Substantial Completion Date*
Construction Schedule Variance from Contract Award**
04/18/2025
12/31/2025
12/01/2025
On-Time (Green)
** Schedule Variance Key:
Red - Current Schedule Variance is > 10% of Original Completion Yellow - Current Schedule Variance is > 5% and Green - Current Schedule Variance is within 5% of Original Completion
Construction Costs
Contract Award Cost Approved Cost Changes Current Construction Contract Cost Cost Variance of Construction Contract* Contract Award Cost Approved Cost Changes Current Construction Contract Cost Cost Variance of Construction Contract**
$3,273,276
$82,265
$3,355,541
On-Budget (Green)
**Cost Variance Key:
Red - Current Construction Costs are > 10% of Contract Award Cost Yellow - Current Construction Costs > 5% and Green - Current Construction Costs are within 5% of Contract Award Cost
Project Schedule Defintions:
Original Contract Completion Date - This is a contractual date, at the time the Contractor is Awarded the contract,representing when the Contractor is obligated to complete all of the work required in the contract and will no longer have a presence within the highway Right-of-Way.
Estimated Substantial Completion Date - This is the day the public (including vehicles and pedestrians) has full and unrestricted use and benefit of the facilities both from the operational and safety standpoint.
This project receives funding from the following sources:
Federal: Yes
State : Yes
Local : No
- Status Text
- Under Construction
- Contact Name
- Heather Tehan
- Contact Text
- Contact Us
If you have questions please contact:
Heather Tehan, PIN-280672
NYSDOT Region 2 Public Information Officer
207 Genesee Street
Utica, NY 13501
Phone: 315-793-2447
- Description
- ## Project Overview
Project Status
- The current status of the project is Under Construction.
- The Bid Opening was on 02/27/2025.
Project Schedule
Award of Contract Original Contract Completion Date*
Estimated Substantial Completion Date*
Construction Schedule Variance from Contract Award** Award of Contract Original Contract Completion Date*
Estimated Substantial Completion Date*
Construction Schedule Variance from Contract Award**
04/18/2025
12/31/2025
12/01/2025
On-Time (Green)
** Schedule Variance Key:
Red - Current Schedule Variance is > 10% of Original Completion Yellow - Current Schedule Variance is > 5% and Green - Current Schedule Variance is within 5% of Original Completion
Construction Costs
Contract Award Cost Approved Cost Changes Current Construction Contract Cost Cost Variance of Construction Contract* Contract Award Cost Approved Cost Changes Current Construction Contract Cost Cost Variance of Construction Contract**
$3,273,276
$82,265
$3,355,541
On-Budget (Green)
**Cost Variance Key:
Red - Current Construction Costs are > 10% of Contract Award Cost Yellow - Current Construction Costs > 5% and Green - Current Construction Costs are within 5% of Contract Award Cost
Project Schedule Defintions:
Original Contract Completion Date - This is a contractual date, at the time the Contractor is Awarded the contract,representing when the Contractor is obligated to complete all of the work required in the contract and will no longer have a presence within the highway Right-of-Way.
Estimated Substantial Completion Date - This is the day the public (including vehicles and pedestrians) has full and unrestricted use and benefit of the facilities both from the operational and safety standpoint.
This project receives funding from the following sources:
Federal: Yes
State : Yes
Local : No
## Description
This project is used to repair, replace or remove hazardous roadside elements (guiderail, bridge rail, trees, etc.) as necessary along highways at various locations in Region 2.
## Location
This project is located in the **Mohawk Valley** region.
**Counties:** Oneida, Madison, Hamilton, Herkimer, Fulton, Montgomery

- Contact Email
- R2Projects@dot.ny.gov
- Contact Phone
- 315-793-2447
- Location Text
- This project is located in the MOHAWK VALLEY region and includes the following:
Counties
ONEIDA
MADISON
HAMILTON
HERKIMER
FULTON
MONTGOMERY
- Bid Opening Raw
- 02/27/2025
- Bid Opening Date
- Feb 27, 2025
- Legislative Text
- Legislative Districts
This project falls within the geographical boundaries of the following legislative districts:
U.S. Senators
Schumer, Charles E.
Gillibrand, Kirsten
U.S. Congressional District data is not currently available.
State Senatorial District data is not currently available.
State Assembly District data is not currently available.