- Scope
- Resurface pavement as needed to improve conditions at the following sites: New York Route 85 in the Town of Bethlehem, Albany County; New York Route 144 in the Town of New Baltimore, New York Route 385 in the Towns of Catskill and Athens, and New York Route 385 in the Town of Coxsackie, Greene County; US Route 4 in the Town of East Greenbush, New York Route 66 in the Town of Sand Lake, and New York Route 67 in the Town of Hoosick, Rensselaer County; New York Route 5 in the Town of Scotia, Schenectady County and New York Route 7 in the City of Schenectady, and New York Route 50 in the Towns of Scotia, East Glenville, Schenectady County.
- Region
- CAPITAL DISTRICT
- Address
- Capital District Region — Greene, Schenectady, Rensselaer, Albany County — NY
- Due Date
- May 30, 2025
- Funding
- Local
- No
- State
- Yes
- Federal
- Yes
- Mpo Text
- Statewide Transportation Improvement Program (STIP)
The Statewide Transportation Improvement Program (STIP) is a list of every project
in New York State for which Federal funding is proposed to be used and that is
scheduled to begin during the designated three Federal fiscal year time frame.
To review the STIP Project List by Region please see the
STIP Project Report .
- Award Raw
- 05/30/2025
- Counties
- Greene, Schenectady, Rensselaer, Albany
- Overview
- Project Overview
Project Status
- The current status of the project is Under Construction.
- The Bid Opening was on 03/27/2025.
Project Schedule
Award of Contract Original Contract Completion Date*
Estimated Substantial Completion Date*
Construction Schedule Variance from Contract Award** Award of Contract Original Contract Completion Date*
Estimated Substantial Completion Date*
Construction Schedule Variance from Contract Award**
05/30/2025
12/18/2026
11/18/2026
On-Time (Green)
** Schedule Variance Key:
Red - Current Schedule Variance is > 10% of Original Completion Yellow - Current Schedule Variance is > 5% and Green - Current Schedule Variance is within 5% of Original Completion
Construction Costs
Contract Award Cost Approved Cost Changes Current Construction Contract Cost Cost Variance of Construction Contract* Contract Award Cost Approved Cost Changes Current Construction Contract Cost Cost Variance of Construction Contract**
$12,622,705
$0
$12,622,705
On-Budget (Green)
**Cost Variance Key:
Red - Current Construction Costs are > 10% of Contract Award Cost Yellow - Current Construction Costs > 5% and Green - Current Construction Costs are within 5% of Contract Award Cost
Project Schedule Defintions:
Original Contract Completion Date - This is a contractual date, at the time the Contractor is Awarded the contract,representing when the Contractor is obligated to complete all of the work required in the contract and will no longer have a presence within the highway Right-of-Way.
Estimated Substantial Completion Date - This is the day the public (including vehicles and pedestrians) has full and unrestricted use and benefit of the facilities both from the operational and safety standpoint.
This project receives funding from the following sources:
Federal: Yes
State : Yes
Local : No
- Status Text
- Under Construction
- Contact Name
- Scott Cook
- Contact Text
- Contact Us
If you have questions please contact:
Scott Cook, PIN-181147
NYSDOT Region 1 Public Information Officer
50 Wolf Road
Albany, NY 12232
Phone: 518-485-7768
- Description
- ## Project Overview
Project Status
- The current status of the project is Under Construction.
- The Bid Opening was on 03/27/2025.
Project Schedule
Award of Contract Original Contract Completion Date*
Estimated Substantial Completion Date*
Construction Schedule Variance from Contract Award** Award of Contract Original Contract Completion Date*
Estimated Substantial Completion Date*
Construction Schedule Variance from Contract Award**
05/30/2025
12/18/2026
11/18/2026
On-Time (Green)
** Schedule Variance Key:
Red - Current Schedule Variance is > 10% of Original Completion Yellow - Current Schedule Variance is > 5% and Green - Current Schedule Variance is within 5% of Original Completion
Construction Costs
Contract Award Cost Approved Cost Changes Current Construction Contract Cost Cost Variance of Construction Contract* Contract Award Cost Approved Cost Changes Current Construction Contract Cost Cost Variance of Construction Contract**
$12,622,705
$0
$12,622,705
On-Budget (Green)
**Cost Variance Key:
Red - Current Construction Costs are > 10% of Contract Award Cost Yellow - Current Construction Costs > 5% and Green - Current Construction Costs are within 5% of Contract Award Cost
Project Schedule Defintions:
Original Contract Completion Date - This is a contractual date, at the time the Contractor is Awarded the contract,representing when the Contractor is obligated to complete all of the work required in the contract and will no longer have a presence within the highway Right-of-Way.
Estimated Substantial Completion Date - This is the day the public (including vehicles and pedestrians) has full and unrestricted use and benefit of the facilities both from the operational and safety standpoint.
This project receives funding from the following sources:
Federal: Yes
State : Yes
Local : No
## Description
Resurface pavement as needed to improve conditions at the following sites: New York Route 85 in the Town of Bethlehem, Albany County; New York Route 144 in the Town of New Baltimore, New York Route 385 in the Towns of Catskill and Athens, and New York Route 385 in the Town of Coxsackie, Greene County; US Route 4 in the Town of East Greenbush, New York Route 66 in the Town of Sand Lake, and New York Route 67 in the Town of Hoosick, Rensselaer County; New York Route 5 in the Town of Scotia, Schenectady County and New York Route 7 in the City of Schenectady, and New York Route 50 in the Towns of Scotia, East Glenville, Schenectady County.
## Location
This project is located in the **Capital District** region.
**Counties:** Greene, Schenectady, Rensselaer, Albany

- Contact Email
- R1Projects@dot.state.ny.us
- Contact Phone
- 518-485-7768
- Location Text
- This project is located in the CAPITAL DISTRICT region and includes the following:
Counties
GREENE
SCHENECTADY
RENSSELAER
ALBANY
Villages
SCOTIA
ATHENS
CATSKILL
COXSACKIE
- Bid Opening Raw
- 03/27/2025
- Bid Opening Date
- Mar 27, 2025
- Legislative Text
- Legislative Districts
This project falls within the geographical boundaries of the following legislative districts:
U.S. Senators
Schumer, Charles E.
Gillibrand, Kirsten
U.S. Congressional District(s)
19th Congressional District (Josh Riley)
20th Congressional District (Paul Tonko)
21st Congressional District (Elise Stefanik)
State Senatorial District(s)
41st Senatorial District (Michelle Hinchey)
43rd Senatorial District (Jacob Ashby)
44th Senatorial District (James Tedisco)
46th Senatorial District (Patricia Fahy)
State Assembly District(s)
102nd Assembly District (Chris Tague)
107th Assembly District (Scott Bendett)
108th Assembly District (John T. McDonald III)
110th Assembly District (Phil Steck)
111th Assembly District (Angelo Santabarbara)
112th Assembly District (Mary Beth Walsh)