1.04 DESCRIPTION OF WORK
A. The project consists of furnishing all materials, labor and equipment necessary
to demolish existing Sewage Pump Station and construct proposed Sewage
Pumping Station No. 0812 as indicated on plans, the work includes but it is not
limited to, excavation, demolition and modification work; removal of existing
pumps, motors, valves, piping and fittings; partially removal and backfilling of
existing dry well and wet well structures; removal of wet well and dry well top
slabs and access hatches; removal of existing power/control panel and
concrete slab; removal of existing telemetry antenna and remote terminal unit
equipment; existing electric service to remain, meter and main disconnect;
removal, transport, salvage and legal disposal of demolition material and
equipment; transportation and handling costs, including removal of salvaged
equipment to a location designated by the Engineer; removal and replacement
of existing PVC sanitary sewer main; furnish, install, operate, and remove
temporary sewage effluent bypass pumps, equipment and accessories; furnish
and install valve vault structure, top slab and access hatch; furnish and install
new wet well structure, top slab and access hatch; furnish and install new
sanitary manhole structure, frame and cover; furnish and place suitable backfill
material; furnish and install two 15 HP submersible pumps and related
equipment; furnish and install leveler control system and related equipment;
furnish and install valve vault sump pump and related equipment; furnish and
install new water service piping, enclosure and accessories; furnish and install
backflow prevention device; coordinate with FPL for installation of electrical
service; furnish and install meter and main disconnect; furnish and install the
proposed power/control system inclusive of the necessary electrical panel,
enclosure, telemetry system and related equipment; install RTU panel and
SCADA equipment furnished by the Department; furnish and install RTU and
01 11 00-3 SCADA materials not specifically provided by the Department; electrical work;
mechanical work; furnish all materials, equipment and supplies necessary for
pump station startup and testing; furnish and install sewage force main pipe
and fittings; connection to existing sewage force main; placing asphalt
driveway; furnish and install landscape improvements as indicate on plans;
temporary and permanent replacement of any sod, sidewalk, pavement and/or
driveway damaged by construction; site restoration; and other appurtenant and
miscellaneous items and work for a complete, satisfactory and functional installation.
Sewage Pump Station 0812 located at 8401 SW 107 Avenue, Miami, Florida 33173,
Section 32, Township 54, Range 40.
B. It is the intent of the Department to obtain a complete and working installation
under this Project and any items of labor, equipment or materials which may
reasonably be assumed as necessary to accomplish this end shall be supplied
whether or not they are specifically shown on the Plans or stated herein.
1.07 MINIMUM REQUIREMENTS OF THE BIDDER
A. Qualifications shall be submitted with the Bids. Submit experience history with a minimum of
references along with the bid. The work shall have been completed with the Contractor’s own forces
or key personnel.
B. The Contractor shall submit to WASD at the time of submitting the bid, name of the Manufactured
and the time it takes to create a product and deliver it to the job site, if the Bids submitted
without entry the name of Manufactured and the Lead Time, will be considered non-responsive.
(if apply)
For CICC 7040 MCC Contracts - CICC 7360 MCC Contracts - Open Competitive Contracts
A. License Requirements
B. Primary Trade Related Work
For a project like a sanitary sewer pump station, the “primary trade
related work” is the work directly related to the sanitary sewer
system/functionality. Examples of such work would include the
installation of gravity sewer mains, manholes, wet wells, valve vaults,
force mains, etc. (all underground improvements). “Non-primary trade
related work” would include items such as electrical, concrete, asphalt,
sodding, fencing, etc.
CICC 7040 MCC Contracts - CICC 7360 MCC Contracts:
a. In accordance with "Issuance of Work Under the Contract" and
"Subcontracting of Work: Post Award", E., of the "Special
Conditions," this Project might be considered a multiple trade
project. None of the primary trade related work shall be
subcontracted. Only ancillary work required to complete this
Project may be subcontracted with prior approval from the
Department and the Miami-Dade County Internal Services Department.
Open Competitive Contracts:
a. This Project might be considered a multiple trade project. None
of the primary trade related work shall be subcontracted. Only
ancillary work required to complete this Project may be
subcontracted with prior approval from the Department
1.08 MINIMUM CONSTRUCTION EXPERIENCE OF THE CONTRACTOR
A. With his bid, the successful Bidder shall submit proof that his/her firm has at least
the minimum successful contract experience as required below for this Contract
being bid. Such proof shall consist of a list of projects, completed prior to the bid
date, with the names and telephone numbers of the owners or representatives that
the OWNER can contact to confirm the listed experience.
B. In addition to submittal requirements stated elsewhere, to qualify for work on
this Contract, the Bidder shall be experienced in raw sewage pump station
construction, including the installation of submersible pumps, and low voltage
electrical power systems.
C. The Bidder must have successfully completed the installation of a minimum of
three (3) pump stations within the last seven (7) years, with at least one (1) within
a private property easement.
D. The Bidder must demonstrate that it has full-time personnel with the necessary
experience to perform the Project’s Scope of Work. The Bidder shall provide a list
of no less than three (3) references who can confirm that the bidder has
successfully upgraded pump stations. Each reference shall include the following:
contact’s name, telephone number, e-mail address, and location of pump
stations.
E. The experience of key senior personnel with other firms may be counted toward
the experience requirement, if acceptable to the ENGINEER. Should such
evidence not be satisfactory to the ENGINEER, whose decision shall be final.
F. The Bidder or Bidder’s By-pass Pumping subcontractor or vendor shall have
established, operated and maintained at least three (3) successful by-pass
pumping operations, including at least (1) by-pass pumping operation receiving
flows from two different Manholes. The Contractor shall have had primary
responsibility for the by-pass operation and the operation shall have been
completed successfully without spills or overflow. Submit experience history with
the Bid Package. A Prime Contractor may bid the project with a qualified
subcontractor that will be responsible for the by-pass pumping operation. The
qualifications of the subcontractor shall be submitted with the bid. The Prime
Contractor shall be responsible for having the qualified subcontractor for the
duration of the project, no change to the qualified subcontractor used for by-pass
pumping shall be made without the approval of the Engineer.
G. In the event a firm is established by executives, supervisors and other senior
field staff (key employees) that would have met these minimum experience
requirements with a prior firm, OWNER reserves the right to qualify the firm
based on OWNER''s sole determination and evaluation of the knowledge and prior
experience of these key employees employed by the new firm. The experience of
key senior personnel with other firms may be counted towards the experience
requirement, if acceptable to the ENGINEER. Should such evidence not be
satisfactory to the ENGINEER, whose decision shall be final, the bid will be
considered non-responsive, and the second lowest bidder will be considered for
award. The qualifying proof shall be submitted in a separate sealed envelope with
the bid.
H. Experience
For each project listed, the pipe installation shall have been
completed and accepted by the project owner prior to the bid
submittal date.
The description must identify for each project:
issued by the client and available Contractor's performance evaluations.
Technical Certification Requirements:
General Building Contractor, General Engineering, Underground Utility/Excavation, Pipelines
The work includes excavation, demolition and modification, removal of pumps, motors, valves, piping, dry well and wet well partial removal and backfilling, removal of slabs, hatches, power/control panel, telemetry and RTU equipment, removal and replacement of PVC sanitary sewer main, temporary bypass pumping, new valve vault, wet well, manhole, backfill, two 15 HP submersible pumps, level control, sump pump, water service and backflow device, FPL coordination, meter and disconnect, power/control panel, telemetry, RTU and SCADA installation, electrical and mechanical work, startup and testing, force main installation and connection, asphalt driveway, landscaping, replacement of sod, sidewalk, pavement and driveway, and site restoration for a complete functional installation.
We post new plumbing opportunities in Florida as agencies publish them. Get them in one email — free, and unsubscribe whenever.
Read from this solicitation’s own documents — each row shows the exact quote it was matched to. Confirm final amounts and forms with the issuing agency before you submit.
A surety’s written statement that it expects to bond you up to a stated amount, subject to final underwriting. It’s what a GC or agency asks to see before they take your bid seriously.
Source: Miami-Dade County Strategic Procurement Department (solicitation MCC-7360-RPQ-No-P16319), retrieved via a public procurement portal. View the official posting, and always confirm requirements and deadlines with the issuing agency.