The construction of approximately ± 6,460 LF of 10" C900 Class 150 PVC water main, ±5 10" mechanical joint ductile iron gate valves, ± 8, 3-way fire hydrant assemblies, ± 2 connections to existing water mains, ± 13 SY concrete removal and replacement, ±51 SY of Class A pavement removal and replacement, erosion control, and all appurtenances necessary for a complete job.
AB-1
ADVERTISEMENT FOR BIDS
Sealed bids will be received for the 2025 CDBG, Water System Improvements: CDBG No.
25p-y-039-1-6784, at Crawford County Board of Commissioners, 640 Georgia Highway 128, Roberta,
Georgia, 31078 until __September 1, 2026__at 11 a.m., at which time they will be publicly opened
and read.
The work under this Contract will consist generally of the following:
The construction of approximately ± 6,460 LF of 10” C900 Class 150 PVC water main, ±5 10”
mechanical joint ductile iron gate valves, ± 8, 3-way fire hydrant assemblies, ± 2 connections to
existing water mains, ± 13 SY concrete removal and replacement, ±51 SY of Class A pavement
removal and replacement, erosion control, and all appurtenances necessary for a complete job.
All work on the Project must be completed within 180 consecutive calendar days of date of
notice to proceed.
Bid shall be submitted on Bid Proposal Forms furnished for that purpose, in accordance with
the Contract Documents and the Plans and Specifications which are on file and may be reviewed by
appointment only at the office of Hofstadter and Associates, Inc., Consulting Engineers, 4571
Arkwright Road, Macon, Georgia 31210.
Copies of Bid Forms, Plans, Specifications and Contract Documents may be obtained from
Hofstadter and Associates, Inc. Consulting Engineers, 4571 Arkwright Road, Macon, Georgia 31210,
upon deposit of $ 200.00 per set. No refund will be made for returned documents.
The work includes the construction of approximately 6,460 LF of 10-inch C900 Class 150 PVC water main, 5 10-inch mechanical joint ductile iron gate valves, 8 3-way fire hydrant assemblies, 2 connections to existing water mains, 13 SY of concrete removal and replacement, 51 SY of Class A pavement removal and replacement, erosion control, and all appurtenances necessary for a complete job. All work must be completed within 180 consecutive calendar days of the date of notice to proceed.