We post new asphalt opportunities in Georgia as agencies publish them. Get them in one email — free, and unsubscribe whenever.
This is an invitation to submit a bid to Lamar County for the 2026 ROCK SPRINGS PROJECTS (including Rock Springs Road, Chappell Mill Road and High Falls Road) as indicated herein. Sealed bids will be received at the office of the Chairman (in Lamar County Administration Building at the above address) up to 2:00 p.m., September 4, 2026 at which time they will be opened and publicly read.
This project will be funded with 2026 LMIG and SPLOST funds. Construction includes Turn Lane Installations at 4 separate locations as outlined in different plan sets, Asphalt Patching, Shoulder Widening and Resurfacing on Rock Springs Road (0.99 mi), Chappell Mill Road (3.23mi) and High Falls Road (2.62 mi) within Lamar County. The work will include construction of turn lanes at Rock Springs Road at Chappell Mill Road (Site #1), Rock Springs Church (Site #2), Rock Springs Church Road at High Falls (Site # 3), Chappell Mill Road at Rock Springs Church entrance (Site # 4), with 335 tons of asphalt patching, 2,217 tons of 19mm asphalt shoulder paving, 3,750 tons of OGI, and 5,954 tons of 9.5mm resurfacing (Rock Springs, Chappell Mill and High Falls Roads) and striping. All work shall conform to the Georgia Department of Transportation's (GDOT) Standard Specifications Construction of Transportation Systems, Current Edition; GDOT's Supplemental Specifications Construction of Transportation Systems, Current Edition; and all applicable GDOT Standards and Details; and other contract requirements, specifications and general conditions.
Bid Documents may be obtained at the County Office Location by appointment. Proposers are encouraged to request Bid Documents via email. All proposers requesting plans and bid documents will be emailed bid documents and/or granted access to the Engineer's FTP site containing digital copies of plans, specifications, and addenda. No documents will be mailed. Request for Bid Documents and any questions regarding the project or to schedule an appointment to pick-
The work includes construction of turn lanes at four locations: Rock Springs Road at Chappell Mill Road (Site #1), Rock Springs Church (Site #2), Rock Springs Church Road at High Falls (Site #3), and Chappell Mill Road at Rock Springs Church entrance (Site #4). It also includes 335 tons of asphalt patching, 2,217 tons of 19mm asphalt shoulder paving, 3,750 tons of OGI, and 5,954 tons of 9.5mm resurfacing on Rock Springs Road (0.99 mi), Chappell Mill Road (3.23 mi), and High Falls Road (2.62 mi), along with striping. All work must conform to GDOT Standard Specifications and Supplemental Specifications.
Source: Georgia Procurement Registry (solicitation PE-77070-NONST-2027-000000006), retrieved via the Georgia Procurement Registry (DOAS). View the official posting , always confirm requirements and deadlines with the issuing agency.