BID OPENING HAS BEEN POSTPONED UNTIL TUESDAY, OCTOBER 6, 2026 AT 2:00 PM (SEE ADDENDUM NO. 2). Interested parties must obtain updated bid documents directly from the City of Calhoun and must be registered with Andrea Everett (AEverett@calhounga.gov) as a current planholder. Returning bidders will not have to pay for updated bid documents, but they must ask to be included on the new planholders list. Under this project, the Contractor shall furnish all labor, equipment, and materials necessary to construct a two-million gallon concrete pre-stressed ground storage tank with deep foundational supports (i.e. aggregate columns), mixing system, yard piping, fencing, grading, soil stabilization, driveway reconstruction, erosion control measures, and all other miscellaneous appurtenances necessary for a complete installation. Time allotted for completion of work is 240 consecutive calendar days.
Calhoun Utilities Project No. 358
New 2MG Ground Storage Tank Revised August 2026
at Fire Tower Road (Brogdon)
00100-1
INVITATION TO BID
PART 1. GENERAL
1.1 SEALED BIDS
Sealed bids for construction of the New 2MG Ground Storage Tank at Fire Tower Road
(Brogdon) will be received until Friday, September 4, 2026 at 10:00 am, inside the
Utilities Training Room at the Calhoun Utilities Building, 700 West Line St., Calhoun,
GA 30701, at which time and place they will be publicly opened and read. Any proposal
received after said time and date will not be considered by the Owner. No bid may be
withdrawn after the closing time for the receipt of bids for a period of sixty (60) days.
1.2 SCOPE OF WORK
Under this project, the Contractor shall furnish all labor, equipment, and materials necessary
to construct a two million-gallon concrete pre-stressed ground storage tank with deep
foundational supports (i.e. aggregate columns), mixing system, yard piping, fencing,
grading, soil stabilization, driveway reconstruction, erosion control measures, and all other
miscellaneous appurtenances necessary for a complete installation. Time allotted for
completion of work is 240 consecutive calendar days. All Work shall be completed in
accordance with the plans and specifications. The Work will be awarded in one (1)
Contract.
1.3 PLANS, SPECIFICATIONS AND CONTRACT DOCUMENTS
Plans, Specifications and Contract Documents are on file for public viewing at the Calhoun
Utilities Engineering Department office located at the 700 West Line St., Calhoun, GA
30701. Copies MUST be obtained through the City of Calhoun Purchasing Department,
Andrea L. Everett, Phone: (706) 602-5682 or aeverett@calnet-ga.net, upon payment of $125
(non-refundable) for each set of printed bid documents or the digital copy.
The Contractor shall furnish all labor, equipment, and materials necessary to construct a two million-gallon concrete pre-stressed ground storage tank with deep foundational supports (i.e. aggregate columns), mixing system, yard piping, fencing, grading, soil stabilization, driveway reconstruction, erosion control measures, and all other miscellaneous appurtenances necessary for a complete installation. Time allotted for completion of work is 240 consecutive calendar days.
We post new materials & suppliers opportunities in Georgia as agencies publish them. Get them in one email — free, and unsubscribe whenever.
Read from this solicitation’s own documents — each row shows the exact quote it was matched to. Confirm final amounts and forms with the issuing agency before you submit.
Source: Georgia Procurement Registry (solicitation PE-76500-NONST-2027-000000025), retrieved via the Georgia Procurement Registry (DOAS). View the official posting, and always confirm requirements and deadlines with the issuing agency.