This is a combined synopsis/solicitation for commercial items prepared in accordance with the format in FAR Part 12. This announcement constitutes the only solicitation; quotations are being requested, and a separate written solicitation will not be issued.
Solicitation number 1240LU26Q0122 is issued as a Request for Quotation (RFQ) for installing 2 way sewer cleanouts.
North American Industry Classification (NAICS): 237110 Water and Sewer Line and Related Structures Construction , Size Standard is $45.0 M.
Set Aside: 100% small business set-aside.
Project Magnitude: $25,000 to $100,000
Bid Bond/Offer Guarantee (FAR 52.228-1): 20% required if quote/offer in excess of $150,000
Performance & Payment Bonds (FAR 52.228-15): Both required at 100% of original contract price if value in excess of $150,000, due 10 days after award. Only payment protections required for contracts exceeding $35,000 but not exceeding $150,000, irrevocable letter of credit or payment bond allowed per FAR 52.228-13, due within 10 days of contract award.
Provide quote by: 12:00 PM, Mountain Time on September 16, 2026.
DOCUMENTS TO RETURN:
The following documents shall be submitted by the quoter for evaluation to be considered responsive:
Schedule of Items
The attached experience questionnaire or a document demonstrating recent and relevant experience and past performance in respect to the size and scope of this particular project. See pages 20-22 for specific information to include for evaluation.
Bid guarantee per information above.
Acknowledge Amendments (per the instructions in Block 11 on the SF-30) if applicable.
Send quote to: Forest Service, Property and Procurement Services, Intermountain Zone, CSA #9
Attn: Alisha Knaub
E-mail: alisha.knaub@usda.gov
For solicitation questions contact Alisha Knaub at email alisha.knaub@usda.gov.
Questions are due no later than September 11, 2026, at 12:00 PM Mountain Time. This will ensure enough time to respond before the solicitation period ends. Please include the solicitation name and number as the subject line of the email.
A site visit is scheduled for September 10th at 1:00 pm at the Sula Work Center. RSVP to the contracting officer at alisha.knaub@usda.gov by COB September 9th.
Amendment 001 - Add updated plans, posted 9/3/2026
Questions and Answers - posted 9/3/2026
The work includes excavating and trenching, erosion and dewatering control measures, removing and disposing of existing structures, installing PVC pipe, PVC 45 degree Wye Combination fittings and related appurtenances, placing and pouring concrete, and compacting pipe bedding and backfill. The contractor must also repair an existing separation in the line at the West Fork Residence while installing the new cleanouts. All work must conform to the Montana Public Works Standard Specifications and the project specifications. The contractor is responsible for obtaining all permits and fees, locating and protecting utilities, and coordinating with government employees and residents.
We post new plumbing opportunities in Montana as agencies publish them. Get them in one email — free, and unsubscribe whenever.
"US""US""59840""HAMILTON""MT""USA""BITTERROOT NATIONAL FOREST""1801 NORTH FIRST STREET""1240LU26Q0122Amendment001.pdf"85787"file"".pdf""1""2026-09-03T18:06:36.541+00:00""5d5d037677dc47b0a96ca428dc8e243e""public""0""public""3fbeab91c6c543f7bfd5e4157a25c9b0""0"13"0""Attachment1.1240LU26Q0122PlansDrawingsAmend001Updated.pdf"1678287"file"".pdf""1""2026-09-03T18:06:36.541+00:00""7c2c320da2bc4a34964793f8538282c5""public""0""public""1a9b71aeb17d407ba2b17703aa9944de""0"12"0""1240LU26Q0122QandA9.3.2026.pdf"76774"file"".pdf""1""2026-09-03T18:06:36.541+00:00""b6f65cccfd82434180a32971915a8df1""public""0""public""b6946d5b9da240629d8af10977989194""0"10"0""1240LU26Q0122.pdf"455317"file"".pdf""1""2026-08-24T17:39:14.184+00:00""c1dc2ba730ef44f6b1b241b70b14df84""public""0""public""ab6b3019b406456cb7fa10f7a575bda7""0"9"0""Attachment1.1240LU26Q0122PlansDrawings.pdf"2252424"file"".pdf""1""2026-08-24T17:39:14.184+00:00""8f98b952897f4a12b08bc0f4750c44ad""public""2026-09-03T18:06:36.541+00:00""1""public""c9063cb3b0884d74bc4dc248df178388""0"8"0""2026-09-03T18:06:36.541+00:00""Attachment2.1240LU26Q0122Specs.pdf"523706"file"".pdf""1""2026-08-24T17:39:14.184+00:00""05ad7c7845ed45dca76ca534d3109465""public""0""public""1ee542590a0f4faea5eef09528043639""0"6"0""Attachment3.1240LU26Q0122WD.pdf"2021961"file"".pdf""1""2026-08-24T17:39:14.184+00:00""8ee24d78952f475196b580871aa6ec44""public""0""public""891f75c4d4ab4275bd0716ce30436b1c""0"5"0""Attachment4.1240LU26Q0122ExperienceQuestionnaire.pdf"91906"file"".pdf""1""2026-08-24T17:39:14.184+00:00""12f31c2bba49484b8b227c9f973e986b""public""0""public""b1d112c8d50949e4a230014f901e4c78""0"1"0"Read from this solicitation’s own documents — each row shows the exact quote it was matched to. Confirm final amounts and forms with the issuing agency before you submit.
Source: SAM.gov (notice 57e1e8caf4514ecfb65e1319cb295900), retrieved via the SAM.gov Get Opportunities API. View the official posting, and always confirm requirements and deadlines with the issuing agency.