September 1st, 2026 - Solicitation post updated to attach site visit sign in sheet and questions and answers.
Amentment 0001 - 1. Update the site visit date, RFI due date and Quote due date as listed below.
Organized Site Visit:
An organized site visit will be held on August 24th, 2026 at 10:00am Local time. From Eager, travel west from the intersection of Central Ave and Main St on AZ-Hwy 260 for approximately 3.1 miles. Turn left (south) onto AZ-Hwy 261 and continue for approximately 17.9 miles. At the intersection with AZ-Hwy 273 turn left (south) onto AZ-Hwy 273 and continue for approximately 2.5 miles. AZ-Hwy 273 turns to NFSR 249 (Three Forks Road). Continue on NFSR 249 for approximately 0.7 miles. Turn right (south-west) onto NFSR 249E and continue for approximately 0.7 miles to the intersection with NFSR 24. This project begins here and proceeds approximately 13 miles south till the NFSR 24 intersection with NFSR 26.
Requests For Information (RFI’s):
Questions shall be submitted via email to troy.mccullough@usda.gov and are due no later than September 3rd, 2026, at 1:00 PM Central Daylight Time. This will ensure enough time to respond before the solicitation period ends. Please include the solicitation name and number as the subject line of the email.
Proposal Due Date:
All proposals shall be emailed to the Contract Specialist at troy.mccullough@usda.gov no later than September 14th, 2026, 1:00 PM Central Daylight Time.
The USDA Forest Service, Apache—Sitgreaves National Forests, Springerville, Arizona, has a requirement for NFSR 24 Road Reconditioning, Aggregate Surfacing, and Road Stabilization on the Alpine Ranger District, Apache County, Arizona. Work is outlined in FP-24 Section 312 Dust Palliative and includes reestablishing the road template on NFSR 24, and stabilizing road surface aggregate with 80/20 Lignosulphonate/Mag Chloride Blend product. Placement will take place on NFSR 24 from intersection with the NFSR249E to the intersection of road with NFSR 26 (MP 13).
Key dates:
Site Visit: August 24th at 10:00 AM Local Time
RFI's Due: September 3rd at 1:00 PM Central Daylight Time
Quotes Due: September 14th at 1:00 PM Central Daylight Time
Work is outlined in FP-24 Section 312 Dust Palliative and includes reestablishing the road template on NFSR 24, and stabilizing road surface aggregate with 80/20 Lignosulphonate/Mag Chloride Blend product. Placement will take place on NFSR 24 from intersection with the NFSR249E to the intersection of road with NFSR 26 (MP 13). The contractor shall furnish labor, material, equipment, tools, transportation, and supplies necessary to complete the work. Specific tasks include blading and shaping the roadbed, applying lignin at 0.5 gal/yd² over a width of 22' for 13 miles, road reconditioning including blading, ripping and/or scarifying to reestablish a roadbed crown of 3-5%, pulling existing shoulders and ditch line to create new shoulder and ditch line (maximum total roadway including shoulders not to exceed 22'), and installing and maintaining all temporary traffic control for the length of the project.
We post new asphalt opportunities in Arizona as agencies publish them. Get them in one email — free, and unsubscribe whenever.
"US""US""871023498""Albuquerque""NM""USA""333 Broadway BLVD SE""127EAX26Q0081 Questions and Answers.docx"17292"file"".docx""1""2026-09-01T14:55:28.778+00:00""36c14531e872459cb19c2cd73f240e15""public""0""public""3a5900e7e7f74ed6872039562024200e""0"33"0""NFSR 24 Stabilization and Preservation Site Visit.pdf"16758"file"".pdf""1""2026-09-01T14:55:28.778+00:00""11356a3ce8c84f6eac6893b7941f8ee3""public""0""public""d46445e9990043eab9bc4d40526bcf95""0"32"0""127EAX26Q0081 Amendment 00001.pdf"155129"file"".pdf""1""2026-08-11T20:26:41.932+00:00""0938f6353a2341f4b063859c63413685""public""0""public""8ba940fe5d40425a8799adc28a435979""0"31"0""127EAX26Q0081 - NFSR 24 Stabilization.pdf"280825"file"".pdf""1""2026-07-28T20:49:14.014+00:00""9d173a329ef14af5a4ec952dab640f7b""public""0""public""5c886aee12294a86b37c188959d570b0""0"30"0""Attachment 1 - Statement of Work.docx"24121"file"".docx""1""2026-07-28T20:49:14.014+00:00""b7d9183b25e8438190cacb83677f925c""public""0""public""c1c8b29ab597420a8b4b84509156dc7c""0"29"0""Attachment 2 - Specifications.pdf"214083"file"".pdf""1""2026-07-28T20:49:14.014+00:00""32382d9eb074440abcf35abe46cbcb9d""public""0""public""3095bc16545146d2966cb055314d6b30""0"28"0""Attachment 3 - Supplemental Specifications.pdf"356277"file"".pdf""1""2026-07-28T20:49:14.014+00:00""e8329848616547bc80d8f365b626e163""public""0""public""57ee869397034f9fbc4b9b70540cc934""0"27"0""Attachment 4 - Schedule of Items.xlsx"11153"file"".xlsx""1""2026-07-28T20:49:14.014+00:00""fb802131a05b4d2eba868686b1eef076""public""0""public""e6a6c23748e94b6f98b08408ea96dafd""0"26"0""Attachment 5 - Maps.pdf"721401"file"".pdf""1""2026-07-28T20:49:14.014+00:00""d1fa0dae56d548ad9784e0c75f50b528""public""0""public""1aa7d60f6c9545a9972faaa379b08be4""0"25"0""Attachment 6 - Exhibit 6.pdf"1148360"file"".pdf""1""2026-07-28T20:49:14.014+00:00""aa70e4a756044e1c868e697d732e96c6""public""0""public""efaac92e599041ab804feda0bf77fc1c""0"24"0""Attachment 7 - Dust Palliative.pdf"86674"file"".pdf""1""2026-07-28T20:49:14.014+00:00""7d276b0c3b254aa89a196e2d3ae283cf""public""0""public""a3c9e0b6f45c4791baf361de77314812""0"8"0""Attachment 8 - Wage Determination.pdf"176368"file"".pdf""1""2026-07-28T20:49:14.014+00:00""db4106f15f65479a89ae4ba6b8d5071b""public""0""public""340c33c9dbda4817b41baf1e4c746e1c""0"7"0"Read from this solicitation’s own documents — each row shows the exact quote it was matched to. Confirm final amounts and forms with the issuing agency before you submit.
Source: SAM.gov (notice f875de2c5da54391a0e248c60266b1bc), retrieved via the SAM.gov Get Opportunities API. View the official posting, and always confirm requirements and deadlines with the issuing agency.