We post new general contractors opportunities in Oklahoma as agencies publish them. Get them in one email — free, and unsubscribe whenever.
**4 August 2026: **
Please see the attached RFP (FA8137-26-R-0040) and all attachments.
THIS POSTING WILL SATISFY THE REQUIREMENT OF RFO 5.101, Presolicitation
Multiple Award Construction Contract (MACC) for General Construction Services will accomplish a broad range of sustainment, maintenance, repair, alteration/renovation, and minor construction projects affecting real property facilities at Tinker Air Force Base, Oklahoma. The work performed will be complex in nature, require multiple construction trades, and may require engineering design performed by credentialed professionals.
Project execution methods will fall into one of the following classifications. The execution method will be defined in the project documents for each Task Order (TO) under this Indefinite Delivery Indefinite Quanity (IDIQ) contract.
Design Build will include the Contractor providing both the design and construction services for a project; during the Design-Build process, final design solutions are provided by the Contractor, not the Government. The Government will provide a Statement of Work (SOW), drawings, and other preliminary documents to establish requirements from the work to be completed. These documents will be equivalent to a schematic 15% or greater design. When awarded the TO for the project, the Contractor will complete the design to the 100% level to include drawings, specifications, design analysis/narrative, and other documentation as required by the Government.
Construction with Limited Design method will include the Government providing the design and the Contractor will further develop portions as required and will provide construction services for the project. This method will be used for non-complex or repetitive work types of projects where design cost and effort is not warranted. The Government will provide the SOW, drawings, and other documents as necessary to establish requirements to complete the project. These documents will be equivalent to a design submittal 35% to 65%. When awarded the TO the Contractor will complete any additional design efforts required by the project and produce a set of working documents for use during construction.
Construction only method will include the Government providing 100% design package, including the SOW, drawings, specification, and any other documents as necessary to establish requirements for the work to be accomplished. When awarded the TO the Contractor shall commence with construction in accordance with the design and contract requirements.
The Contractor is required to furnish all materials, labor, plant, tools, transportation, equipment, testing services, quality control, and incidentals necessary to provide a complete useable end product as specified in the TO/project documents.
The North American Industry Classification System (NAICS) Code is 236210, Industrial Building Construction with a small business size standard of $45 million.
The MACC will be executed for one base period of five (5) years with one option period of five (5) years.
The Government will negotiate equitable adjustments resulting from change orders in the shortest practicable time. Approximately 120 days are required to definitize equitable adjustments associated with change orders for construction. The definitization of an equitable adjustment begins when the contracting officer receives an adequate change order definitization proposal and ends when the contracting officer executes a contractual action to definitize the change order.
IMPORTANT NOTICE: Offerors are required to complete their registration in the System for Award Management (SAM) database via the website https://www.sam.gov. Offerors are strongly encouraged to review their informaiton in SAM to validate that it is current and up to date. Failure to do so could result in the offeror being ineligible for award of Department of War contracts IAW RFO 4.203-1 registered in SAM database.
DISCLAIMER: The information being requested does not constitute a commitment on the part of the Government to award a contract, nor to pay for any costs incurred as a result of replying to this notice. This notice should not be construed as a commitment by the Government for any purpose.
The contractor will furnish all materials, labor, plant, tools, transportation, equipment, testing services, quality control, and incidentals to provide a complete useable end product as specified in Task Order/project documents. Work may be performed under Design-Build, Construction with Limited Design, or Construction only methods, and may require engineering design by credentialed professionals. The contract is an Indefinite Delivery Indefinite Quantity (IDIQ) contract with a base period of five years and one option period of five years.
"73145-9125""TINKER AFB""OK""USA""CP 405 739 4040""7858 5TH ST STE 1""Attachment_3_Section_M_Evaluation_Criteria 29 July 26.pdf"212857"file"".pdf""1""2026-08-04T16:48:37.956+00:00""797247cc67ee49ddae4433cb0ecafc38""public""0""public""ad91b43649f5482b9e6c54e3198497a7""0"27"0""Attachment_2__Section_L 29 Jul 26.pdf"233439"file"".pdf""1""2026-08-04T16:48:37.956+00:00""f169539459b943d1b34ddfb07e6045eb""public""0""public""1813dc7cb44c40d6ba4ca66a730880d9""0"26"0""Attachment_2b_Appendix_B_Work_Sample_Cover_Sheet4May26.docx"31547"file"".docx""1""2026-08-04T16:48:37.956+00:00""5e119737bd914794a491d4f76edbd059""public""0""public""8150fe9dac02410ba7b3bdd76759f727""0"25"0""Attachment_2f_Appendix_F_MACC_FOCross_Reference_Matrix 4 May 26.xlsx"85613"file"".xlsx""1""2026-08-04T16:48:37.956+00:00""61c72c7cf7304419969ad67ca75b48d3""public""0""public""de5a8498dfd24a0bb9bb896392d46c03""0"25"0""Attachment_2a_Appendix_A_Corporate_Relationships_and_Structures4May26.xlsx"15865"file"".xlsx""1""2026-08-04T16:48:37.956+00:00""95fe747d103a46ffa9e29e2b642b4eee""public""0""public""ace8fcec0ac44e5b8f19e650574b1301""0"24"0""Attachment_2d_Appendix_D_MACC_FOSelf_Scoring_Matrix 06 May 26.xlsx"85538"file"".xlsx""1""2026-08-04T16:48:37.956+00:00""db5ec0817a314c1596a160218f083a0a""public""0""public""6f96e492639d4c71b733d74a948dbd59""0"24"0""Attachment_2c_Appendix_C_MACC_SBSelf_Scoring_Matrix 06 May 26.xlsx"84280"file"".xlsx""1""2026-08-04T16:48:37.956+00:00""e58a6e73c4424172ab4e8cb0dab6ee2b""public""0""public""eb8e9f59ee514318b197779d1e4743d5""0"24"0""Attachment_2e_Appendix_E_MACC_SBCross_Reference_Matrix 4 May 26.xlsx"89766"file"".xlsx""1""2026-08-04T16:48:37.956+00:00""97399d57fd57404cb3b2564eb3976da6""public""0""public""0ea3e566100d443cb606b1880a59ead2""0"24"0""001 CDRL - Organization Chart Signed.pdf"147417"file"".pdf""1""2026-08-04T16:48:37.956+00:00""fd73434872534398b88706424c9bbff1""public""0""public""5a0c191291ae40dc82226681478ed118""0"23"0""004 CDRL Data Rights.pdf"101882"file"".pdf""1""2026-08-04T16:48:37.956+00:00""5722ab89d1ff4c1f8c816f697d5aac90""public""0""public""cf017eefc44e42399a649956d392ff90""0"22"0""003 CDRL - TO Progress Mtg Signed.pdf"147315"file"".pdf""1""2026-08-04T16:48:37.956+00:00""2a0c3eb3efbe425da04497e49ceaf8f4""public""0""public""7e9612d97ee24aab80c60df9317c2526""0"21"0""002 CDRL - Quaterly Progress Mtg Signed.pdf"147668"file"".pdf""1""2026-08-04T16:48:37.956+00:00""a98ad92ff26043c2be6b33ea46cbd2f4""public""0""public""ccdda9b928d44c60844ea9dafbb47da9""0"20"0""ERDCITL_TR12-1_r2.pdf"3581884"file"".pdf""1""2026-08-04T16:48:37.956+00:00""82a48f3c35314d00926bd465fe9019ce""public""0""public""ccb7efc5639c41a5820cd52fab144a96""0"19"0""ERDCITL_TR12-6_r6.pdf"1615217"file"".pdf""1""2026-08-04T16:48:37.956+00:00""9b9b4c216a7c4e99827b19c002547424""public""0""public""875808dd797a4fab9eee9b8efa2bc30e""0"18"0""tinkerafb_INRMP_App G.pdf"4829636"file"".pdf""1""2026-08-04T16:48:37.956+00:00""e32ad713c726453487a8c5b7d6623527""public""0""public""56780d67e6404d43b356204fb1e3488f""0"17"0""afi91-202_afmcsup.pdf"2829970"file"".pdf""1""2026-08-04T16:48:37.956+00:00""5a4fd3246f0144a68b922b19bd80306b""public""0""public""cce0e955369942f68254389e652fdc39""0"16"0""tinkerafbi13-204.pdf"1842601"file"".pdf""1""2026-08-04T16:48:37.956+00:00""c7d22aed872d40ecb4726012c3a13d50""public""0""public""cd4d2595592b4a2cbf38a1370f09ff9c""0"15"0""TAFB_SOP_outages_v2.pdf"484279"file"".pdf""1""2026-08-04T16:48:37.956+00:00""850c4ed34f73429880da84939d4719b3""public""0""public""45b5958ac1c746f6a9e8cf0cc6922d8c""0"14"0""tinkerafbi21-100.pdf"218566"file"".pdf""1""2026-08-04T16:48:37.956+00:00""dd4694b562af45dba8971fe0b70d5372""public""0""public""865a60e53e064e08be403c4bdfb13d34""0"13"0""dodio-2000.16v1_afi10-245-o.pdf"38270"file"".pdf""1""2026-08-04T16:48:37.956+00:00""0ddd932d61cd469ea69f76c97d8f5768""public""0""public""c6989430199c422b839bd32fde524870""0"12"0""tinkerafb_INRMP_App E.pdf"230760"file"".pdf""1""2026-08-04T16:48:37.956+00:00""d9589d84b967485d8190d213ab05ddd4""public""0""public""43c83323db0e40cab5c033ef6ba67c28""0"11"0""UFC Binder 1.pdf"108578136"file"".pdf""1""2026-08-04T16:48:37.956+00:00""fbfe8fdfe1304f8596c22bf0d0298710""public""0""public""7bc5854134d4495384cb3215c3c01343""0"10"0""TAFB Gen Specs Reference 1.pdf"40664980"file"".pdf""1""2026-08-04T16:48:37.956+00:00""f550371cb0254ef6807120d71d2e5a51""public""0""public""1fbecaad3f494f718f597b3397793907""0"9"0""afi48-104.pdf"324968"file"".pdf""1""2026-08-04T16:48:37.956+00:00""dc9c190ae92b4bc9aaf12f7bc8fc2d93""public""0""public""43365de103b94ea8ac01e62c18775367""0"8"0""Appendix C UMRL.pdf"702008"file"".pdf""1""2026-08-04T16:48:37.956+00:00""516cbbf4d6954e74a7dc9e4c1d5acc25""public""0""public""d3d7eda8e50f4f48b4c1e09759b4e0dc""0"7"0""TAFB Facility Standards.pdf"10552268"file"".pdf""1""2026-08-04T16:48:37.956+00:00""a6f79638439a411f93b2aff5d1c11aa2""public""0""public""7bec53667ce348b88f7b05edaa36658c""0"6"0""B2 -TAFB Technical Requirements Div 02-48.pdf"10261125"file"".pdf""1""2026-08-04T16:48:37.956+00:00""c868f2452a21491ebf6b91a5f7c0dac8""public""0""public""7c4421322ddb413ab5a08a58901b42b6""0"5"0""Appendix B1 TAFB General Requirements Div 00-01.pdf"10269631"file"".pdf""1""2026-08-04T16:48:37.956+00:00""db42d81efe8e4eacb9394fb01de94e6f""public""0""public""a89d965f1c924353aa6fd18c7aa55d92""0"4"0""Appendix A - Abbreviations.pdf"61125"file"".pdf""1""2026-08-04T16:48:37.956+00:00""fd8229bb4e754fcbb5e943ba4207c0bb""public""0""public""7ca3b56ad41a4873945df24f59224d5d""0"3"0""Attachment 1 - Statement of Work Jun26.pdf"1065918"file"".pdf""1""2026-08-04T16:48:37.956+00:00""4947bb92f7ad442a947169af86662eb8""public""0""public""96e96eca470d4b4fab54729f808d27a6""0"2"0""Solicitation - FA813726R0040.pdf"1207369"file"".pdf""1""2026-08-04T16:48:37.956+00:00""c628b10f6b2e44eeb84d631b6dd62d49""public""0""public""23173bd48162463f844e825454d3abb4""0"1"0"Read from this solicitation’s own documents — each row shows the exact quote it was matched to. Confirm final amounts and forms with the issuing agency before you submit.