DIV I Base Bid: install approx 3,500 LF of 8” watermain to replace ex. waterlines, replacement of 5 FHs. DIV II – Alt. A - install 2,700 LF 8” to replace ex. waterlines, replacement of 3 FHs. DIV III – Alt. B: install 860 LF of 8” watermain & 135 LF bore & jack 20-inch steel casing with 8” carrier pipe, replacement of 3 FHs.
Delivery Method: Design-Bid-Build
Construction Cost Range: N/A
Documents: American Engineering, 1300 12 St, Ste. A, Cayce, SC 29033
The project includes three divisions: Base Bid installs approximately 3,500 linear feet of 8-inch watermain and replaces 5 fire hydrants; Alternate A installs 2,700 linear feet of 8-inch watermain and replaces 3 fire hydrants; Alternate B installs 860 linear feet of 8-inch watermain, 135 linear feet of bore and jack 20-inch steel casing with 8-inch carrier pipe, and replaces 3 fire hydrants.
We post new plumbing opportunities in South Carolina as agencies publish them. Get them in one email — free, and unsubscribe whenever.
Most South Carolina work asks for the two below, and the solicitation documents are where it’s stated. Here’s what each costs through Light RFP if you need one.
Source: Elloree Water System (solicitation AEC-Project-No.-25-027), retrieved via a public procurement portal. View the official posting, and always confirm requirements and deadlines with the issuing agency.