MetroConnects project will be procured as a Base Bid with an Alternate Bid. The Base Bid includes rehab of approx. 11,100 LF of 8-inch and 1,800 LF of 12-inch using CIPP; including partial CIPP lateral rehab, point repairs, monolithic lining of approx. 210 VF, and associated rehab work. The Alternate Bid includes approx. 380 LF of 8-inch CIPP, 130 LF of 12-inch CIPP, 45 LF of new PVC sewer installation, point repairs, and various manhole rehab work, including 44 LF of monolithic lining.
Delivery Method: Design-Bid-Build
Construction Cost Range: N/A
Documents: Quest No. 10311603; or Dillon Hodge at Dillon.Hodge@KeeferEngineering.com
We post new plumbing opportunities in South Carolina as agencies publish them. Get them in one email — free, and unsubscribe whenever.
Most South Carolina work asks for the two below, and the solicitation documents are where it’s stated. Here’s what each costs through Light RFP if you need one.
Source: Metropolitan Sewer Subdistrict (solicitation 26-4001-B), retrieved via a public procurement portal. View the official posting, and always confirm requirements and deadlines with the issuing agency.