- Scope
- This project replaces 14 traffic signals and 17 embedded signal poles and other equipment at 15 intersections in Broome, Chenango, Otsego, Schoharie, Sullivan, and Tioga Counties.
- Region
- SOUTHERN TIER
- Address
- Southern Tier Region — Tioga, Schoharie, Otsego, Sullivan, Broome, Chenango County — NY
- Funding
- Local
- No
- State
- Yes
- Federal
- Yes
- Mpo Text
- Statewide Transportation Improvement Program (STIP)
The Statewide Transportation Improvement Program (STIP) is a list of every project
in New York State for which Federal funding is proposed to be used and that is
scheduled to begin during the designated three Federal fiscal year time frame.
To review the STIP Project List by Region please see the
STIP Project Report .
- Counties
- Tioga, Schoharie, Otsego, Sullivan, Broome, Chenango
- Overview
- Project Overview
Project Status
- The current status of the project is In Development.
- The Bid Opening is expected to be in Winter 2026/2027.
- Construction is expected to begin in Spring 2027.
- Construction is expected to be completed in Winter 2028/2029.
Cost of the Project
The project cost is approximately $4,500,000.
This project receives funding from the following sources:
Federal: Yes
State : Yes
Local : No
- Status Text
- In Development
- Contact Name
- Daniel Scharfenberger
- Contact Text
- Contact Us
If you have questions please contact:
Daniel Scharfenberger, PIN-9FAS24
NYSDOT Region 9 Public Information Officer
44 Hawley Street
Binghamton, NY 13901
Phone:
- Description
- ## Project Overview
Project Status
- The current status of the project is In Development.
- The Bid Opening is expected to be in Winter 2026/2027.
- Construction is expected to begin in Spring 2027.
- Construction is expected to be completed in Winter 2028/2029.
Cost of the Project
The project cost is approximately $4,500,000.
This project receives funding from the following sources:
Federal: Yes
State : Yes
Local : No
## Description
This project replaces 14 traffic signals and 17 embedded signal poles and other equipment at 15 intersections in Broome, Chenango, Otsego, Schoharie, Sullivan, and Tioga Counties.
## Location
This project is located in the **Southern Tier** region.
**Counties:** Tioga, Schoharie, Otsego, Sullivan, Broome, Chenango

- Contact Email
- R9Projects@dot.state.ny.us
- Location Text
- This project is located in the SOUTHERN TIER region and includes the following:
Counties
TIOGA
SCHOHARIE
OTSEGO
SULLIVAN
BROOME
CHENANGO
Villages
JOHNSON CITY
MORRIS
OWEGO
WURTSBORO
COBLESKILL
ENDICOTT
- Bid Opening Raw
- Winter 2026/2027
- Estimated Value
- 4500000
- Construction End
- Winter 2028/2029
- Legislative Text
- Legislative Districts
This project falls within the geographical boundaries of the following legislative districts:
U.S. Senators
Schumer, Charles E.
Gillibrand, Kirsten
U.S. Congressional District(s)
19th Congressional District (Josh Riley)
21st Congressional District (Elise Stefanik)
State Senatorial District(s)
51st Senatorial District (Peter Oberacker)
52nd Senatorial District (Lea Webb)
58th Senatorial District (Thomas F. O'Mara)
State Assembly District(s)
100th Assembly District (Paula Elaine Kay)
101st Assembly District (Brian Maher)
102nd Assembly District (Chris Tague)
121st Assembly District (Joe Angelino)
122nd Assembly District (Brian D. Miller)
123rd Assembly District (Donna A. Lupardo)
124th Assembly District (Christopher S. Friend)
- Construction Begin
- Spring 2027