Light RFP
Government · Florida

South Dade Landfill Stormwater Improvements

Due Aug 19, 2026·21 days left·Electrical, Paving / SidewalksView official posting ↗
Issuing agency
Miami-Dade County Strategic Procurement Department
Method
Competitive Sealed Bid
Category
Bids & Contracts
PIN
RPQ No 18650-26
Location
Florida
Posted
Jul 20, 2026
Takeaways by LightRFP AI
  • Miami-Dade County seeks a licensed General Contractor or Building Contractor for stormwater improvements at the South Dade Landfill in Homestead, FL.
  • The project includes milling and resurfacing of roads and parking lot, road reconstruction, detention area restoration, grading, drainage, signage, and new electrical service.
  • Bids are due by 8/19/2026 at 2:00 PM via sealed envelopes to the Department of Solid Waste Management.
  • A mandatory pre-bid/site meeting is scheduled for 7/27/2026 at 10:00 AM at 23707 SW 97th Avenue, Homestead, FL 33032.
  • The estimated value is $2,964,993.
  • Requirement: All Contractors must hold a current valid State of Florida Certified General Contractor License, as required by the Florida Building Code, for the types of Work covered by the Contract at the time of RPQ submission.
  • Requirement: A Surety Bid Bond (5% of Total Bid Price) is required for all bids over $200k.
  • Requirement: A Surety Performance and Payment Bond is required for all bids over $200k.
  • Requirement: Liquidated damages are $349.20 per day.
  • Requirement: The contractor must be pre-qualified in the Miscellaneous Construction Contracts (MCC) program at the time of the award.

AI-generated, verify all details against the official documents.

Description

Funding Source: This project is partially funded by the State of Florida Department of Environmental Protection.

Project name: South Dade Landfill Stormwater Improvements
RPQ No. 18650-26
Site Address: 23707 SW 97th Ave., Homestead, FL 33190
Site Hours of Operation: 7:00 AM to 7:00 PM, Monday through Sunday
Work Hours: 7:00 AM to 7:00 PM, Monday through Friday
Special Work Hour Requirements: Construction of the access road from the facility entrance to Cell 5 of the landfill must be performed outside of the site’s hours of operation to avoid interference with ongoing operations. Work that does not hinder facility operations may be conducted between 7:00 a.m. and 7:00 p.m., Monday through Friday; however, all proposed work hours, including any exceptions, must be reviewed and approved by the County prior to the commencement of construction activities.

Purpose:
The Miami Dade County’s Department of Solid Waste Management (DSWM) South Dade Landfill has a 30-acre site, including administration and operational areas that are currently experiencing stormwater management issues. Existing conditions include ponding along the access road and areas south of the administration building. The County is seeking a licensed General Contractor or Building Contractor to improve and restore the stormwater management system within the project area.

Description of Work:
The project consists of furnishing all labor, materials and equipment necessary for roadway and stormwater improvements at the South Dade Landfill. The scope includes, but is not limited to, the following:
• Milling and resurfacing of on-site and off-site roads
• Road reconstruction of on-site and off-site roads
• Milling and resurfacing of the parking lot
• Restoration of existing detention areas
• Grading and drainage improvements
• Upgrading and restoring signage and pavement markings
• Installation of a new electrical service

General Requirements:
• The Contractor shall coordinate with the Facility Supervisor and the Engineer of Record (EOR) to phase the work in a manner that minimizes disruptions to facility operations, equipment, and circulation of vehicles.
• Facility operations shall remain uninterrupted during the site’s normal operating hours.

Technical Certification Requirements:
General Building Contractor, Building Contractor

Documents3
RPQ_No_18650-26.pdfPDF
BID_DOCS_RPQ18650-26.pdfPDF
PRE-BID_SITE_VISIT_SIGN_IN_SHEET_RPQ18650-26.pdfPDF

Contact

Address
Miami-Dade County, FL
Full source recordfrom Miami-Dade County Strategic Procurement Department
Detail
Title
South Dade Landfill Stormwater Improvements
Technical Cert
General Building Contractor, Building Contractor
Opening Date Full
8/19/2026 2:00:00 PM
Announcement Info
Funding Source: This project is partially funded by the State of Florida Department of Environmental Protection. Project name: South Dade Landfill Stormwater Improvements RPQ No. 18650-26 Site Address: 23707 SW 97th Ave., Homestead, FL 33190 Site Hours of Operation: 7:00 AM to 7:00 PM, Monday through Sunday Work Hours: 7:00 AM to 7:00 PM, Monday through Friday Special Work Hour Requirements: Construction of the access road from the facility entrance to Cell 5 of the landfill must be performed outside of the site’s hours of operation to avoid interference with ongoing operations. Work that does not hinder facility operations may be conducted between 7:00 a.m. and 7:00 p.m., Monday through Friday; however, all proposed work hours, including any exceptions, must be reviewed and approved by the County prior to the commencement of construction activities. Purpose: The Miami Dade County’s Department of Solid Waste Management (DSWM) South Dade Landfill has a 30-acre site, including administration and operational areas that are currently experiencing stormwater management issues. Existing conditions include ponding along the access road and areas south of the administration building. The County is seeking a licensed General Contractor or Building Contractor to improve and restore the stormwater management system within the project area. Description of Work: The project consists of furnishing all labor, materials and equipment necessary for roadway and stormwater improvements at the South Dade Landfill. The scope includes, but is not limited to, the following: • Milling and resurfacing of on-site and off-site roads • Road reconstruction of on-site and off-site roads • Milling and resurfacing of the parking lot • Restoration of existing detention areas • Grading and drainage improvements • Upgrading and restoring signage and pavement markings • Installation of a new electrical service General Requirements: • The Contractor shall coordinate with the Facility Supervisor and the Engineer of Record (EOR) to phase the work in a manner that minimizes disruptions to facility operations, equipment, and circulation of vehicles. • Facility operations shall remain uninterrupted during the site’s normal operating hours.
Listing
Title
South Dade Landfill Stormwater Improvements
Posted Date
07/20/2026
Opening Date
08/19/2026
Solicitation Type
Bids & Contracts
Solicitation Number
RPQ No 18650-26
Enriched
Yes

Source: Miami-Dade County Strategic Procurement Department (solicitation MIAMI_DADE_SPD-RPQ-No-18650-26), retrieved via a public procurement portal. View the official posting — always confirm requirements and deadlines with the issuing agency.