Louisiana · Baton Rouge, LA

Avenue Street Albert Pipe Liner

Due Jul 28, 2026·Due today·Bridge / InfrastructureView official posting ↗
Issuing agency
Non State - St. Tammany Parish Government
Method
Competitive Sealed Bid
PIN
923456-26-22-1
Location
Baton Rouge, LA
Posted
Jul 10, 2026
Takeaways by LightRFP AI
  • St. Tammany Parish Government is seeking sealed quotes for the Avenue Street Albert Pipe Liner project.
  • The project is classified as Highway, Street and Bridge Construction.
  • Sealed quotes are due by 2:00 p.m. on Tuesday, July 28, 2026.
  • The place of performance is Baton Rouge, LA.
  • The procurement method is Competitive Sealed Bid.
  • Requirement: The contractor shall hold the classification of Highway, Street, and Bridge Construction.
  • Requirement: For projects costing $25,000 or more, the successful respondent shall provide a performance bond in the amount of 100% of the project cost.
  • Requirement: If the estimated cost of the work is $50k or more, the bidder must provide a State Contractor’s License Number.

AI-generated, verify all details against the official documents.

Description

Agency: Non State - St. Tammany Parish Government — Purchasing

ST. TAMMANY PARISH
MICHAEL B. COOPER
PARISH PRESIDENT
PROCUREMENT DEPARTMENT
P.O. BOX 628 | COVINGTON, LOUISIANA| 70434 | PROCUREMENT@STPGOV.ORG | 985-898-2520
WWW.STPGOV.ORG
Version 2026.1
NOTICE OF QUOTE REQUEST
ST. TAMMANY PARISH
Sealed quotes will be received by the Department of Procurement until 2:00 p.m., Tuesday, July
28, 2026, and then opened at that time by the Procurement Staff for the following project:
Quote # 26-22-1 – Avenue Street Albert Pipe Liner
This Quote package is available online at www.bidexpress.com or LaPAC
https://wwwcfprd.doa.louisiana.gov/osp/lapac/dspBid.cfm?search=department&term=185.It is
the Vendor’s responsibility to check Bid Express or LaPAC frequently for any possible addenda
that may be issued. The Parish is not responsible for a vendor’s failure to download any addenda
documents required to complete a submission.
The project classification is:
Highway, Street and Bridge Construction
Paper Quotes must be sealed. In addition, the outside of the envelope, box, or package containing
the Quote should be marked with the following information. Name and Address, State
Contractor’s License Number (if the estimated cost of the work is $50k or more), Quote Number,
and the Quote Name. Quotes submitted without this information may be deemed non-responsive.
Quotes will be received by the St. Tammany Parish Government Department of Procurement,
located at 21454 Koop Dr., Suite 2F, Mandeville LA. 70471 from each quoter or his agent and
given a written receipt, by certified mail with return receipt requested, or electronically at
www.bidexpress.com.
The Procurement Department can be contacted by telephone at (985) 898-2520, or via e-mail at
Procurement@stpgov.org. St. Tammany Parish Government reserves the right to reject any or all
quotes and to w

Documents1
9031300.pdfPDF

Contact

Name
Shawn Hoover
Phone
985-898-2520
Address
21454 Koop Dr, Suite 2F, Mandeville, LA 70471
Full source recordfrom Louisiana LaPAC
Title
Avenue Street Albert Pipe Liner
Contact
Email
sdhoover@stpgov.org
Phone
985-898-2520
Address
21454 Koop Dr, Suite 2F, Mandeville, LA 70471
Section
Purchasing
Department
Non State - St. Tammany Parish Government
Contact Name
Shawn Hoover
Excerpt
ST. TAMMANY PARISH MICHAEL B. COOPER PARISH PRESIDENT PROCUREMENT DEPARTMENT P.O. BOX 628 | COVINGTON, LOUISIANA| 70434 | PROCUREMENT@STPGOV.ORG | 985-898-2520 WWW.STPGOV.ORG Version 2026.1 NOTICE OF QUOTE REQUEST ST. TAMMANY PARISH Sealed quotes will be received by the Department of Procurement until 2:00 p.m., Tuesday, July 28, 2026, and then opened at that time by the Procurement Staff for the following project: Quote # 26-22-1 – Avenue Street Albert Pipe Liner This Quote package is available online at www.bidexpress.com or LaPAC https://wwwcfprd.doa.louisiana.gov/osp/lapac/dspBid.cfm?search=department&term=185.It is the Vendor’s responsibility to check Bid Express or LaPAC frequently for any possible addenda that may be issued. The Parish is not responsible for a vendor’s failure to download any addenda documents required to complete a submission. The project classification is: Highway, Street and Bridge Construction Paper Quotes must be sealed. In addition, the outside of the envelope, box, or package containing the Quote should be marked with the following information. Name and Address, State Contractor’s License Number (if the estimated cost of the work is $50k or more), Quote Number, and the Quote Name. Quotes submitted without this information may be deemed non-responsive. Quotes will be received by the St. Tammany Parish Government Department of Procurement, located at 21454 Koop Dr., Suite 2F, Mandeville LA. 70471 from each quoter or his agent and given a written receipt, by certified mail with return receipt requested, or electronically at www.bidexpress.com. The Procurement Department can be contacted by telephone at (985) 898-2520, or via e-mail at Procurement@stpgov.org. St.
Pdf Text
ST. TAMMANY PARISH MICHAEL B. COOPER PARISH PRESIDENT PROCUREMENT DEPARTMENT P.O. BOX 628 | COVINGTON, LOUISIANA| 70434 | PROCUREMENT@STPGOV.ORG | 985-898-2520 WWW.STPGOV.ORG Version 2026.1 NOTICE OF QUOTE REQUEST ST. TAMMANY PARISH Sealed quotes will be received by the Department of Procurement until 2:00 p.m., Tuesday, July 28, 2026, and then opened at that time by the Procurement Staff for the following project: Quote # 26-22-1 – Avenue Street Albert Pipe Liner This Quote package is available online at www.bidexpress.com or LaPAC https://wwwcfprd.doa.louisiana.gov/osp/lapac/dspBid.cfm?search=department&term=185.It is the Vendor’s responsibility to check Bid Express or LaPAC frequently for any possible addenda that may be issued. The Parish is not responsible for a vendor’s failure to download any addenda documents required to complete a submission. The project classification is: Highway, Street and Bridge Construction Paper Quotes must be sealed. In addition, the outside of the envelope, box, or package containing the Quote should be marked with the following information. Name and Address, State Contractor’s License Number (if the estimated cost of the work is $50k or more), Quote Number, and the Quote Name. Quotes submitted without this information may be deemed non-responsive. Quotes will be received by the St. Tammany Parish Government Department of Procurement, located at 21454 Koop Dr., Suite 2F, Mandeville LA. 70471 from each quoter or his agent and given a written receipt, by certified mail with return receipt requested, or electronically at www.bidexpress.com. The Procurement Department can be contacted by telephone at (985) 898-2520, or via e-mail at Procurement@stpgov.org. St. Tammany Parish Government reserves the right to reject any or all quotes and to waive informalities. QUOTE REQUEST ST. TAMMANY PARISH GOVERNMENT AVENUE ST ALBERT PIPE LINER Quote Number: 26-22-1 Quote Deadline: Tuesday, July 28, 2026 July 6, 2026 TABLE OF CONTENTS PART I: OVERVIEW ................................................................................................................. 1 1.1 Background ..................................................................................................................1 1.2 Definitions ....................................................................................................................1 1.3 Schedule of Events.......................................................................................................1 1.4 Quote Submittal............................................................................................................2 PART II: SCOPE OF WORK/SERVICES .................................................................................. 3 2.1 Scope of work/Services ................................................................................................3 2.2 Period of Agreement.....................................................................................................3 2.3 Price Schedule .............................................................................................................3 2.4 Deliverables..................................................................................................................3 2.5 Licensing Required .......................................................................................................3 PART III: EVALUATION ............................................................................................................ 4 PART IV: PERFORMANCE STANDARDS ................................................................................ 4 4.1 Performance Requirements ..........................................................................................4 4.1.1 Shop drawings, Brochures and Samples .............................................................. 4 4.1.2 Record Drawings .................................................................................................. 5 4.1.3 Progress of Work .................................................................................................. 5 4.1.4 The Parish’s Right to Proceed with Portions of the Work ...................................... 6 4.1.5 Time of Completion ............................................................................................... 6 4.1.6 Extensions of Time for Change Orders ................................................................. 8 4.1.7 Liquidated Damages ............................................................................................. 8 4.1.8 Labor, Materials, Equipment, Supervision, Permits and Taxes ............................. 9 4.1.9 Quantities of Estimate, Changes in Quantities, Extra Work ..................................11 4.1.10 Injuries to Persons and Property ..........................................................................12 4.1.11 Sanitary Provisions ..............................................................................................15 4.1.12 Rights of Way ......................................................................................................15 4.1.13 Protection and Restoration of Property and Landscape .......................................16 4.1.14 Contractor’s Responsibility for Work ....................................................................17 4.1.15 Tests and Inspections; Correction and Removal of Defective Work .....................17 4.1.16 Subsurface Conditions .........................................................................................19 4.1.17 Removal and Disposal of Structures and Obstructions ........................................19 4.1.18 The Parish’s Right to Occupancy .........................................................................20 4.1.19 Survey Horizontal and Vertical Control ................................................................21 4.2 Compliance With Applicable Laws ..............................................................................21 4.3 Site Visitation..............................................................................................................21 PART V: GENERAL PROVISIONS ..........................................................................................21 5.1 Legibility/Clarity ..........................................................................................................21 5.2 Confidential Information, Trade Secrets, and Proprietary Information .........................21 5.3 Quote Clarifications Prior to Submittal ........................................................................23 5.3.1 Pre-Quote Conference .........................................................................................23 5.3.2 Respondent Inquiry Periods .................................................................................23 5.4 Errors and Omissions in Quote ...................................................................................23 5.5 Performance Bond......................................................................................................24 5.6 Changes, Addenda, Withdrawals................................................................................25 5.7 Withdrawal of Quote ...................................................................................................25 5.8 Material in the Quote Request ....................................................................................25 5.9 Waiver of Administrative Informalities .........................................................................25 5.10 Quote Rejection ..........................................................................................................25 5.11 Ownership of Quote....................................................................................................26 5.12 Cost of Offer Preparation ............................................................................................26 5.13 Non-negotiable Contract Terms ..................................................................................26 5.14 Taxes .........................................................................................................................26 5.15 Quote Validity .............................................................................................................26 5.16 Prime Contractor Responsibilities ...............................................................................26 5.17 Use of Subcontractors ................................................................................................26 5.18 Written or Oral Discussions/Presentations ..................................................................27 5.19 Acceptance of Quote Content .....................................................................................27 5.20 Evaluation and Selection ............................................................................................27 5.21 Contract Negotiations .................................................................................................28 5.22 Contract Award and Execution ...................................................................................28 5.23 Notice of Intent to Award ............................................................................................28 5.24 Affidavits.....................................................................................................................28 5.25 Insurance Requirements.............................................................................................29 5.26 Subcontractor Insurance.............................................................................................33 5.27 Indemnification and Limitation of Liability ....................................................................34 5.27.1 Duty to Defend…………………………………………………………………………..34 5.27.2 Contractor Liabilitiy……………………………………………………………………...34 5.27.3 Force Majeure…………………………………………………………………………...34 5.27.4 Indemnification…………………………………………………………………………...34 5.27.5 Intellectual Property Indemnification………………………………………………......34 5.28 Payment .....................................................................................................................35 5.28.1 Payment for Services ...........................................................................................35 5.28.2 Acceptance and Final Payment(s) .......................................................................36 5.29 Termination ................................................................................................................38 5.29.1 Termination of the Contract for Cause .................................................................38 5.29.2 Termination of the Contract for Convenience .......................................................38 5.29.3 Termination for Non-Appropriation of Funds ........................................................38 5.29.4 Effects of Termination ..........................................................................................38 5.29.5 Default of Contractor ............................................................................................38 5.30 Assignment.................................................................................................................40 5.31 No Guarantee of Quantities ........................................................................................40 5.32 Audit of Records .........................................................................................................39 5.33 Civil Rights Compliance ..............................................................................................40 5.34 Record Retention........................................................................................................40 5.35 Record Ownership ......................................................................................................40 5.36 Content of Contract/ Order of Precedence ..................................................................40 5.37 Contract Changes.......................................................................................................40 5.38 Substitution of Personnel ............................................................................................40 5.39 Governing Law ...........................................................................................................41 5.40 Anti-Kickback Clause..................................................................................................41 5.41 Clean Air Act ..............................................................................................................41 5.42 Energy Policy and Conservation Act ...........................................................................41 5.43 Clean Water Act .........................................................................................................41 5.44 Anti-Lobbying and Debarment Act ..............................................................................41 Quote Package includes the following Attachments: Attachment “A” – Pricing Sheet, Unit Price Sheet, and Project Specifications Attachment “B” – Sample Contract Attachment “C” – Signage Instructions (Omitted) Attachment “D” – Insurance Requirements Attachment “E” – Affidavits Attachment “F” – Sample Corporate Resolution Attachment “G” – Sample Certificate of Insurance 1 QUOTE REQUEST FOR AVENUE ST ALBERT PIPE LINER PART I: OVERVIEW 1.1 Background The Parish requests a Contractor to provide all adequate and competent labor, equipment, tools, and materials necessary to improve drainage by cleaning existing pipe and installing pipe liner as specified between 810 and 814 Avenue St. Albert (R03A021) located in Covington, Louisiana. 1.2 Definitions A. Shall – The term “shall” denotes mandatory requirements. B. Must - The term “must” denotes mandatory requirements. C. May - The term “may” denotes an advisory or permissible action. D. Should – The term “should” denotes a desirable action. E. Contractor – A Respondent who contracts with the Parish. F. Parish - St. Tammany Parish Government. G. Discussions- For the purposes of this Quote Request, a formal, structured means of conducting written or oral communications/presentations with responsible Respondents who submit quotes in response to this Quote Request. H. Quote Request – The Quote Request and any attachments and amendments thereto. I. Respondent – Person or entity responding to this Quote Request. J. Agreement – A contract between the Contractor and the Parish. 1.3 Schedule of Events Date Time (CT) Quote Due Date July 28, 2026 2:00 PM Inquiry Deadline July 21, 2026 2:00 PM Addendum Deadline July 23, 2026 2:00 PM 2 NOTE: The Parish reserves the right to revise this schedule. Any such revision will be formalized by the issuance of an addendum to the Quote Request. 1.4 Quote Submittal The Quote package is available online www.bidexpress.com or LaPAC https://wwwcfprd.doa.louisiana.gov/osp/lapac/pubmain.cfm. It is the Contractor’s responsibility to check Bid Express or LaPAC frequently for any possible addenda that may be issued. The Parish is not responsible for a Contractor’s failure to download any addenda documents required to complete a submission. All quotes shall be in writing and shall be received by the Procurement Department no later than the date and time shown in the Schedule of Events. Important - - Clearly mark outside of the sealed envelope, box or package with the following information and format. Quotes without this information may be deemed non-responsive: Χ Name and Address of the Quoter Χ The State Contractor’s License Number of the Quoter (if the work is estimated at $50k or more) Χ Quote Request Name: AVENUE ST ALBERT PIPE LINER Χ Quote Request #: 26-22-1 Χ Quote Due Date: TUESDAY, JULY 28, 2026 Quotes may only be sent via certified mail, hand-delivery or courier service to our physical location at: St. Tammany Parish Government Procurement Department 21454 Koop Drive, Suite 2F Mandeville, Louisiana 70471 Respondent is solely responsible for ensuring that its courier service Contractor makes inside deliveries to our physical location. The Parish is not responsible for any delays caused by the Respondent’s chosen means of proposal delivery. Respondent is solely responsible for the timely delivery of its proposal. Failure to meet the Quote Due Date shall result in rejection of the quote. In the event that Contractor is a member of a corporation, partnership, L.L.C., L.L.P., or any other juridical entity, as an additional provision, Contractor should supply a certified copy of a corporate resolution or other written evidence of authority of person signing the quote/proposal. QUOTES SHALL BE OPENED PUBLICLY AT THE PHYSICAL LOCATION IDENTIFIED ABOVE AND ONLY RESPONDENTS SUBMITTING QUOTES SHALL BE IDENTIFIED ALOUD. 3 PART II: SCOPE OF WORK/SERVICES 2.1 Scope of Work/Services The Contractor must provide all adequate and competent labor, equipment, tools, and materials necessary to improve drainage by cleaning existing pipe and installing pipe liner as specified between 810 and 814 Avenue St. Albert (R03A021) located in Covington, Louisiana. The Parish reserves the right to add, remove or otherwise modify the above, as determined necessary by the Parish and as allowed by law. The time period for completion of the project is thirty (30) calendar days from the issuance of the Notice to Proceed (NTP). Any work that may be reasonably inferred from the specifications or drawings as being required to produce the intended result shall be supplied whether or not it is specifically called for. Work, materials or equipment described herein which so applied to this project are covered by a well- known technical meaning or specification shall be deemed to be governed by such recognized standards unless specifically excluded. If the contractor has not done business with the Parish, the contractor should submit a W-9 with their response. 2.2 Period of Agreement The term of any contract resulting from this solicitation shall begin on the date of the Parish President’s signature or approval in writing by the Parish President or designee. The contract shall terminate pursuant to the terms and conditions of section 5.30 herein, the terms and conditions of the contract, operation of law, as agreed between the parties, or upon satisfactory completion of all services and obligations described in the contract. 2.3 Price Schedule Prices quoted by the Respondent shall be firm for the term of the contract. 2.4 Deliverables The deliverables listed in this section are the minimum desired from the successful Respondent. Every Respondent should describe what deliverables will be provided per their quote and how the proposed deliverables will be provided. 2.5 Licensing Required Contractor shall hold the following classification: Highway, Street, and Bridge Construction. If the estimated cost of the work is $50k or more a Contractor licensed by the State to do the type of work indicated in Section 2.1 may submit a quote. The Respondent’s signature on the quote certifies that he holds an active license under the provisions of Chapter 24 of the Louisiana Revised Statutes, Title 37. Failure to be properly licensed constitutes authority for the Parish to 4 reject the quote. The Parish reserves the right to require a Contractor licensed for less than $50k depending on the requiements set forth in Section 2.1 and shall provide within 10 days after being notified of an Award. PART III: EVALUATION The quotes will be evaluated in light of the material and the substantiating evidence presented to the Parish, not on the basis of what may be inferred. The lowest monetary quote in compliance with the Quote Request will be awarded the contract. Only for the purpose of interpretation of the quote, when applicable, written words shall govern if a conflict exists between words and numerals. PART IV: PERFORMANCE STANDARDS 4.1 Performance Requirements 4.1.1 Shop drawings, Brochures and Samples After checking and verifying all field measurements, Contractor shall submit to the Parish for approval, five copies (or at the Parish's option, one reproducible copy) of all shop drawings, which shall have been checked by and stamped with the approval of Contractor and identified as the Parish may require. The data shown on the shop drawings will be complete with respect to dimensions, design criteria, materials of construction and the like to enable the Parish to review the information as required. Contractor shall also submit to the Parish, for review with such promptness as to cause no delay in work, all samples as required by the contract documents. All samples will have been checked by and stamped with the approval of Contractor identified clearly as to material, manufacturer, any pertinent catalog numbers and the use for which intended. At the time of each submission, Contractor shall in writing call the Parish's attention to any deviations that the shop drawings or samples may have from the requirements of the contract documents. The Parish will review with reasonable promptness shop drawings and samples, but its review shall be only for conformance with the design concept of the project and for compliance with the information given in the contract documents. The review of a separate item as such will not indicate approval of the assembly in which the item functions. Contractor shall make any corrections required by the Parish and shall return the required number of corrected copies of shop drawings and resubmit new samples for review. Contractor shall direct specific attention in writing or on resubmitted shop drawings to revisions other than the corrections called for by the Parish on previous submissions. Contractor's stamp of approval on any shop drawing or sample shall constitute a representation to the Parish that Contractor has determined and verified all quantities, dimensions, field construction criteria, materials catalog numbers and similar data and thereafter assumes full responsibility for doing so, and that it has reviewed or coordinated each shop drawing or sample with the requirements of the work and the contract documents. Where a shop drawing or sample submission is required by the specifications, no related work shall be commenced until the submission has been reviewed by the Parish. A copy of each reviewed shop drawing and each inspected sample shall be kept in good order by Contractor at the site and shall be available to the Parish. 5 The Parish's review of shop drawings or samples shall not relieve Contractor from its responsibility for any deviations from the requirements of the contract documents unless Contractor has in writing called the Parish's attention to such deviation at the time of submission and the Parish has given written approval to the specific deviation, nor shall any review by the Parish relieve Contractor from responsibility for errors or omissions in the shop drawings. The mere submittal of shop drawings which contain deviations from the requirements of plans, specifications and/or previous submittals in itself does not satisfy this requirement. 4.1.2 Record Drawings The Contractor shall keep an accurate record in a manner approved by the Parish of all changes in the contract documents during construction. In work concerning underground utilities, the Contractor shall keep an accurate record in a manner approved by the Parish of all valves, fittings, etc. Before the work is accepted by the Parish, and said acceptance is recorded, the Contractor shall furnish the Parish a copy of this record. Contractor shall keep an accurate drawing measured in the field to the nearest 0.1' of the location of all sewer house connections. The location shown shall be the end of the connection at the property line measured along the main line of pipe from a manhole. Contractor shall keep an accurate drawing of the storm water drainage collection system. Inverts to the nearest 0.01' and top of castings shall be shown as well as location of all structures to the nearest 0.1'. Upon completion of the work, the plan will be given to the Parish. 4.1.3 Progress of Work Contractor shall conduct the work in such a professional manner and with sufficient materials, equipment and labor as is considered necessary to ensure its completion within the time limit specified. The Parish shall issue a Notice to Proceed to the Contractor within twenty (20) calendar days from the date of execution of the contract. Upon mutual consent by both parties, the Notice to Proceed may be extended. The Contractor is to commence work under the contract within ten (10) calendar days from the date the Notice to Proceed is issued by the Parish. The Contractor, immediately after being awarded the contract, shall prepare and submit for the Parish's approval an estimated progress schedule for the work to be performed, as well as a construction signing layout for all roads within the project area. The Contractor shall not start work or request partial payment until the work schedule has been submitted to the Parish for approval. Revisions to the original schedule will be made based on extension of days granted for inclement weather or change orders issued under the contract. No other revision shall be made which affects the original completion or updated completion date, whichever is applicable. Failure of the Contractor to submit an estimated progress schedule or to complete timely and on schedule the work shown on the progress schedule negates any and all causes or claims by the Contractor for accelerated completion damages. These accelerated damage claims shall be deemed forfeited. 6 Meetings will be held as often as necessary to expedite the progress of the job. Meetings will be held during normal working hours at the jobsite and shall be mandatory for the Contractor and all subcontractors working on the project. Meetings may be requested by the Parish at any time and at the discretion of the Parish. 4.1.4 The Parish’s Right to Proceed with Portions of the Work Upon failure of the Contractor to comply with any notice given in accordance with the provisions hereof, the Parish shall have the alternative right, instead of assuming charge of the entire work, to place additional forces, tools, equipment and materials on parts of the work. The cost incurred by the Parish in carrying on such parts of the work shall be payable by the Contractor. Such work shall be deemed to be carried on by the Parish on account of the Contractor. The Parish may retain all amounts of the cost of such work from any sum due Contractor or those funds that may become due to Contractor under the contract. The Parish may perform additional work related to the project by itself or it may let any other direct contract which may contain similar general conditions. Contractor shall afford the other Contractors who are parties to such different contracts (or the Parish, if it is performing the additional work itself) reasonable opportunity for the introduction and storage of materials and equipment and the execution of work, and shall properly connect and coordinate its work with the subsequent work. If any part of Contractor's work depends upon proper execution or results upon the work of any such other Contractor (or the Parish), Contractor shall inspect and promptly report to the Parish in writing any defects or deficiencies in such work that render it unsuitable for such proper execution and results. Failure to so report shall constitute an acceptance of the other work as fit and proper for the relationship of its work except as to defects and deficiencies which may appear in the other work after the execution of its work. Whatever work is being done by the Parish, other Contractors or by this Contractor, the parties shall respect the various interests of the other parties at all times. The Parish may, at its sole discretion, establish additional rules and regulations concerning such orderly respect of the rights of various interests. Contractor shall do all cutting, fitting and patching of its work that may be required to integrate its several parts properly and fit to receive or be received by such other work. Contractor shall not endanger any work of others by cutting, excavating or otherwise altering work and will only alter work with the written consent of the Parish and of the other Contractors whose work will be affected. If the performance of additional work by other Contractors or the Parish is not noted in the contract documents, written notice thereof shall be given to Contractor prior to starting any such additional work. If Contractor believes that the performance of such additional work by the Parish or others may cause additional expense or entitles an extension of the contract time, the Contractor may make a claim therefor. The claim must be in writing to the Parish within thirty (30) calendar days of receipt of notice from the Parish of the planned additional work by others. 4.1.5 Time of Completion The Notice to Proceed will stipulate the date on which the Contractor shall begin work. That date shall be the beginning of the contract time charges. 7 Contractor shall notify the Parish through its duly authorized representative, in advance, of where Contractor’s work shall commence each day. A daily log shall be maintained by Contractor to establish dates, times, persons contacted, and location of work. Specific notice shall be made to the Parish if the Contractor plans to work on Saturday, Sunday, or a Parish approved holiday. If notice is not received, no consideration will be given for inclement weather and same shall be considered a valid work day. The work covered by the plans, specifications and contract documents must be completed sufficiently for acceptance within the number of calendar days specified in the quote and/or the contract, commencing from the date specified in the Notice to Proceed. It is hereby understood and mutually agreed, by and between the Contractor and the Parish, that the time of completion is an essential condition of the contract, and it is further mutually understood and agreed that if the Contractor shall neglect, fail or refuse to complete the work within the time specified, or any proper extension thereof granted by the Parish, then the Contractor does hereby agree, as partial consideration for the awarding of the contract, to pay the Parish as specified per Table 4.1.7 in the contract, not as a penalty, but as liquidated damages for such breach of contract for each and every calendar day that the Contractor shall be in default after the time stipulated in the contract for completing the work. It is specifically understood that the Parish shall also be entitled to receive a reasonable attorney fee and all costs in the event that Contractor fails to adhere to this agreement and the contract is referred to counsel for any reason whatsoever. Reasonable attorney fees shall be the prevailing hourly rate of the private sector, and in no event shall the hourly rate be less than $175.00 per hour. All attorney fees shall be paid to the operating budget of the Office of the Parish President. Prior to final payment, the Contractor may, in writing to the Parish, certify that the entire project is substantially complete and request that the Parish or its agent issue a certificate of Substantial Completion. The Parish may grant an extension(s) of time to the Contractor for unusual circumstances which are beyond the control of the Contractor and could not reasonably be foreseen by the Contractor prior to submission of its quote. Any such request must be made in writing to the Parish within seven (7) calendar days following the event occasioning the delay. The Parish shall have the exclusive and unilateral authority to determine, grant, and/or deny the validity of any such claim. Extensions of time for inclement weather shall be processed as follows: Commencing on the start date of each job, the Parish Inspector assigned to same shall keep a weekly log, indicating on each day whether inclement weather has prohibited the Contractor from working on any project within the specific job, based upon the following: 1. Should the Contractor prepare to begin work on any day in which inclement weather, or the conditions resulting from the weather, prevent work from beginning at the usual starting time, and the crew is dismissed as a result, the Contractor will not be charged for a working day whether or not conditions change during the day and the rest of the day becomes suitable for work. 2. If weather conditions on the previous day prevent Contractor from performing work scheduled, provided that no other work can be performed on any project within the package. The Parish Inspector shall determine if it is financially reasonable to require the Contractor to deviate from the schedule and relocate to another location. 8 3. If the Contractor is unable to work at least 60% of the normal work day due to inclement weather, provided that a normal working force is engaged on the job. Any dispute of weather conditions as related to a specific job shall be settled by records of the National Weather Service. 4.1.6 Extensions of Time for Change Orders When a change order is issued, the Parish and Contractor will agree on a reasonable time extension, if any, to implement such change. Consideration shall be given for, but not limited to, the following: If material has to be ordered; Remobilization and or relocation of equipment to perform task; and Reasonable time frame to complete additional work. Time extensions for change orders shall be reflected on the official document signed by the Parish and Contractor. At the end of each month, the Parish or its agent will furnish to the Contractor a monthly statement which reflects the number of approved days added to the contract. The Contractor will be allowed fourteen (14) calendar days in which to file a written protest setting forth in what respect the monthly statement is incorrect; otherwise, the statement shall be considered accepted by the Contractor as correct. Apart from extension of time for unavoidable delays, no payment or allowance of any kind shall be made to the Contractor as compensation for damages because of hindrance or delay for any cause in the progress of the work, whether such delay be avoidable or unavoidable. 4.1.7 Liquidated Damages In case the work is not completed in every respect within the time that may be extended, it is understood and agreed that per diem deductions of the sum per Table 4.1.7 for liquidated damages, as stipulated in the quote and/or contract, shall be made from the total contract price for each and every calendar day after and exclusive of the day on which completion was required, and up to the completion of the work and acceptance thereof by the Parish. It is understood and agreed that time is of the essence to the contract, and the above sum being specifically herein agreed upon in advance as the measure of damages to the Parish on account of such delay in the completion of the work. It is further agreed that the expiration of the term herein assigned or as may be extended for performing the work shall, ipso facto, constitute a putting in default, the Contractor hereby waiving any and all notice of default. The Contractor agrees and consents that the contract price, reduced by the aggregate of the entire damages so deducted, shall be accepted in full satisfaction of all work executed under the contract. It is further understood and agreed that Contractor shall be liable for a reasonable attorney fee and all costs associated with any breach of this agreement, including but not limited to this subsection. In the event that any dispute or breach herein causes referrals to counsel, then Contractor agrees to pay a reasonable attorney fee at the prevailing hourly rate of the private sector. In no event shall the hourly rate be less than $175.00 per hour. 9 Table 4.1.7 Liquidated Damages Original Contract Amount Daily Charge Dollars Dollars 0 - 250,000 500 250,000 – 1 Million 1,000 > 1 Million – 5 Million 1,500 > 5 Million – 10 Million 2,000 > 10 Million 3,000 • Parish reserves the right to increase the Daily charge rate due to additional provisions required in order to complete the project as described in the specifications. 4.1.8 Labor, Materials, Equipment, Supervision, Permits and Taxes The Contractor shall provide and pay for all labor, materials, equipment, supervision, subcontracting, transportation, tools, fuel, power, water, sanitary facilities and all incidentals necessary for the completion of the work in substantial conformance with the contract documents. The Contractor shall provide competent, suitably qualified personnel to survey and lay out the work and perform construction as required by the contract documents. It shall at all times maintain good discipline and order at the site. Unless otherwise specifically provided for in the specifications, all workmanship, equipment, materials, and articles incorporated in the work covered by the contract are to be new and of the best grade of their respective kinds for the purpose intended. Samples of materials furnished under the contract shall be submitted for approval to the Parish when and as directed. Whenever a material or article required is specified or shown on the plans by using the name of a proprietary product or of a particular manufacturer or Contractor, any material or article which shall perform adequately the duties imposed by the general design will be considered equal, and satisfactory, providing the material or article so proposed is of equal substance and function and that all technical data concerning the proposed substitution be approved by the Parish prior to the submission of a quote. The Parish shall have the exclusive and unilateral discretion to determine quality and suitability. Materials shall be properly and securely stored so as to ensure the preservation of quality and fitness for the work, and in a manner that leaves the material accessible to inspection. Materials or equipment may not be stored on the site in a manner such that it will interfere with the continued operation of streets and driveways or other Contractors working on the site. 10 The Contractor, by entering into the contract for this work, sets itself forth as an expert in the field of construction and it shall supervise and direct the work efficiently and with its best skill and attention. It shall be solely responsible for the means, methods, techniques, sequences and procedures of construction. Contractor shall keep on the work, at all times during its progress, a competent resident superintendent, who shall not be replaced without written notice to the Parish except under extraordinary circumstances. The superintendent will be Contractor's representative at the site and shall have authority to act on behalf of Contractor. All communications given to the superintendent shall be as binding as if given to the Contractor. The Parish specifically reserves the right to approve and/or disapprove the retention of a new superintendent, all to not be unreasonably withheld. Any foreman or workman employed on this project who disregards orders or instructions, does not perform his work in a proper and skillful manner, or is otherwise objectionable, shall, at the written request of the Parish, be removed from the work and shall be replaced by a suitable foreman or workman. The Contractor and/or its assigned representative shall personally ensure that all subcontracts and divisions of the work are executed in a proper and workmanlike manner, on scheduled time, and with due and proper cooperation. Failure of the Contractor to keep the necessary qualified perso
Segment
72000000
Enriched
Yes
Open Date
07/28/2026 2:00:00 PM CT
Bid Number
923456-26-22-1
Date Issued
07/10/2026

Source: Louisiana LaPAC (bid LOUISIANA-923456-26-22-1), retrieved via the Louisiana Office of State Procurement. View the official posting — always confirm requirements and deadlines with the issuing agency.