The purpose of Amendment 1 is to correct the dates in the RFQ.
All other terms and conditions remain unchanged.
This is a small business set aside for Fiber Optic Newtowrk Rebuild. Please see attached documents.
The contractor must run approximately 18 km of armored, jacketed SMF optic cable with at least 432 fibers (216 pairs) buried underground via directional boring or open trench, install 2-inch HDPE conduit and tracer wire, remove old fiber, terminate fiber within buildings using precision fusion splicing, install and test networking equipment (Cisco pass through switches, 200G/25G optics), install CAT 6A cabling to workstations, and produce as-built drawings. The work is divided into five main phases: Network Design and Engineering, Identify/Procure Equipment, Construction, Networking Equipment Install, and Project Closeout. The contractor will work closely with the ITS Technical Point of Contact.
We post new electrical opportunities in Colorado as agencies publish them. Get them in one email — free, and unsubscribe whenever.
"US""20230""WASHINGTON""DC""USA""ENTERPRISE SVC ORG., OFC OF ACQUIS.""1401 CONSTITUTION AVE, NW""Fiber Optiic Network Amendment 1.pdf"314280"file"".pdf""1""2026-09-10T16:48:11.251+00:00""a3486233fc4e4f3b880745bff4fee449""public""0""public""277f451f07a1433cb6b546e668775d37""0"5"0""Fiber Optiic Network 9.09.26.pdf"313256"file"".pdf""1""2026-09-10T13:08:34+00:00""c764f4537f6a4d3cbaf3510578a3f755""public""0""public""0eb6b98e3353461ea84dde0e93330e2a""0"4"0""SOW-Table Mountain Fiber Optic Network Rebuild.pdf"1677911"file"".pdf""1""2026-09-10T13:08:34+00:00""46193c56ba1a4bfb99f3cd2b19a70999""public""0""public""9f57ed3aea114e49a2ee1ffa0fd2a784""0"3"0""Clauses.pdf"277488"file"".pdf""1""2026-09-10T13:08:34+00:00""42c70f5265c049e4927ad562506f76f8""public""0""public""5d6a9feb22fc43e09ebb61bf2b7d56dd""0"2"0""Wage Determination.pdf"44338"file"".pdf""1""2026-09-10T13:08:34+00:00""a651e86803ab458d9702398046951b52""public""0""public""fa5fb38ca2334a32ba7db51a800d4ee2""0"1"0"Most Colorado work asks for the two below, and the solicitation documents are where it’s stated. Here’s what each costs through Light RFP if you need one.
Source: SAM.gov (notice 6f5b6524525a4805ab3050e2df455c37), retrieved via the SAM.gov Get Opportunities API. View the official posting, and always confirm requirements and deadlines with the issuing agency.