Amendment No.: 0004
Solicitation No.: 36C24126Q0613
Date: July 29, 2026
Purpose of Amendment
The purpose of this amendment is to provide responses to questions submitted regarding the solicitation. As a result of these questions and responses, the response due date remains unchanged.
Answer: Not part of this contract, 20yr lease
Answer: There is leniency on the dates as long as it is prearranged.
Answer: Edwards equipment is proprietary as in it is not “off the shelf” and all Fire Alarm Equipment under the contract is Edwards equipment and tied into the Edwards FireWorks graphical command-and-control software and incident management platform. The contractor must have a certified Edwards FireWorks Programmer for programming, maintenance, and staff training. The company must also have Edwards certified technicians to work on the fire alarm system when required. This is also a measured Performance Standard under the Quality Assurance Surveillance Plan (QASP).
Answer: Yes
Answer: No, there are no restrictions on what regularly scheduled services are performed during specific times. As long as it is scheduled ahead of time. Emergency services which are included in this contract are not restrained to regular business hours though and their specifics are stated in the SOW.
Answer: Yes, emergency services for unforeseen issues that arise. The specific requirements are stated in the SOW, and response times are a measured Performance Standard under the Quality Assurance Surveillance Plan (QASP). There are no regularly scheduled maintenance services that need to be performed after-hours though.
Answer: No, but I can provide the last one for one of the buildings as an example and that most of the gauges are due for replacement. However, they would be due for replacement over the life of the fully executed contract anyways (5 yrs). The inspection provided is for the building 78, one of the largest buildings under the contract. Also, the inventory for the equipment was provided as Attachment A.
Answer: No but I can provide the last one for one of the buildings. The one provided was for building 78, one of the largest buildings under the contract. Also, the inventory for the equipment was provided as an Attachment.
Answer: No, that is covered by the Engineering Service.
Answer: No, all of the spaces to service the Fire Alarm System are regular access or Maintenance Access Areas.
Answer: No, that is covered by the Engineering Service.
Answer: Monitoring services referring to someone for the Fire Alarm Panel to notify when a fire alarm goes off to call the fire department. Then no, we have a separate contractor that monitors the alarms for the system and notifies the fire department.
We do require emergency services as needed and that information is included in the SOW and response times are a measured Performance Standard under the Quality Assurance Surveillance Plan (QASP).
Answer: Yes, that is correct for batteries and fire extinguishers. Although, some of them might need to be replaced at the beginning of the first year.
Answer: Yes, at different times the programming will need updates by a tech that is factory certified.
Answer: Some but most should be included in the contract. It depends on the type, this is detailed in the SOW.
Answer: Yes, repairs identified during testing usually. This is detailed in the SOW.
Answer: Yes, for programming and any panel work respectively, Edwards factory training certification is required.
Answer: Base year, plus 4 additional option years (Refer to Solicitation).
Answer: No, the inventory list was provided as Attachment A and this year’s annual inspections for sprinkler and fire for one building is also being provided.
Answer: Yes, we have remote key activators already for many of the duct smokes.
Answer: The fire extinguisher count provided in the equipment inventory is a 1 for 1 count. That number can go up or down by a few if we renovate space or remove a vehicle from our inventory and no longer need one/two or require another one/two for it as an example. The original purchase would not be required under the contract, but the subsequent inspections and future replacement testing would be required under the contract.
"US""04330""TOGUS""ME""USA""ONE VA CENTER""Amendment 0004_36C24126Q0613.pdf"92346"file"".pdf""1""2026-07-29T14:48:23.843+00:00""18dac464045447bba82aecb3af29b5e2""public""0""public""61c4e5926b79458cbf47f4b38ba666be""0"8"0""Attachment 1_FireScan.pdf"182594"file"".pdf""1""2026-07-29T14:48:23.843+00:00""509fba52b87241569e3e2e930961c2dd""public""0""public""e38aad061f2e4cae99deea95632d220d""0"7"0""Attachment 2_SprinklerScan.pdf"87604"file"".pdf""1""2026-07-29T14:48:23.843+00:00""2752faa2bcfb4f3fa0fb0728250fe9de""public""0""public""662bc082cb4f4b34adecd60fc80223b7""0"6"0""Amendment 0003_36C24126Q0613.pdf"69034"file"".pdf""1""2026-07-27T17:43:59.531+00:00""3d045680a8ee4d8bbfb0397d26c79928""public""0""public""22644a9cc66542999e68a46e7bd3e818""0"5"0""Attachment 1_Equipment List_Amd 0001.pdf"128325"file"".pdf""1""2026-07-22T12:16:03.832+00:00""f285a94dc65a47e29824733a4b0e5d1a""public""0""public""278f3d524f404d79b28cd7efbfadfc97""0"4"0""Attachment 1_Wage Determination.pdf"5414421"file"".pdf""1""2026-07-21T13:23:13.784+00:00""e6118a8622134a129bf0cbc632b486d1""public""0""public""57f9927fe9344d268f96033c70f623e8""0"3"0""CSS_Fire Alarm Maint and Testing_36C24126Q0613.pdf"541529"file"".pdf""1""2026-07-21T13:23:13.784+00:00""3ba55275e589475399f1b3610ee1c1e5""public""0""public""28124056f240413aab7bb71a22e89618""0"2"0""36C24126Q0613.docx"17128"file"".docx""1""2026-07-21T13:23:13.784+00:00""54da7ca5c0d24b5593d45362827546b1""public""0""public""456aed202cbc4275906a52ac94b24743""0"1"0"Source: SAM.gov (notice 4821e6c1b4a84143bfd792cd97d19e00), retrieved via the SAM.gov Get Opportunities API. View the official posting — always confirm requirements and deadlines with the issuing agency.